Fond du Lac County, WI Environmental Rules: Erosion Control (2026)
Key Facts
- Permit threshold
- 4,000 sq ft or more of land disturbance
- Administering agency
- County Land and Water Conservation Department
- Review time
- 20 business days to approve/deny
- Sediment standard
- 5 tons per acre per year on permitted sites
- Penalty
- $100-$500 forfeiture per day of violation
- Permit duration
- 180 days, extendable in 180-day increments
Summary
Land-disturbing construction on 4,000 square feet or more of unincorporated Fond du Lac County requires an erosion and sediment control permit from the County Land and Water Conservation Department under Code Sec. 27-4. Smaller sites still must follow baseline standards, and violators face a forfeiture of $100 to $500 per day under Sec. 27-12.
1.A permit is required for a construction site with 4,000 square feet or greater of land disturbing construction activity. ... Any person violating any of the provisions of this article shall be subject to a forfeiture of not less than $100.00 nor more than $500.00 and the costs of prosecution for each violation. Each day a violation exists shall constitute a separate offense.
Full Breakdown
County Code Chapter 27, Article I regulates soil erosion on active construction sites in unincorporated Fond du Lac County. Adopted under Wis. 07, the ordinance designates the Fond du Lac County Land and Water Conservation Department as the administering authority (Sec. 27-1). Sec. 27-4 sets the trigger: a permit is required for any construction site with 4,000 square feet or more of land-disturbing activity, while smaller sites must still meet the baseline best-management-practice standards in Sec. 27-7(1); the administering authority can also require a permit on a smaller site if needed to protect water quality.
Exemptions include one- and two-family homes disturbing less than an acre outside a common development plan (regulated instead under Wis. Admin. 125), agricultural practice and facility areas, silviculture, most transportation facilities, and routine maintenance disturbing less than five acres. Permit applicants must submit an erosion and sediment control plan meeting Sec. 27-9 and pay the fee set by the County Land Conservation Committee (Sec. 27-10); the department has 20 business days to approve or deny a complete application, and failure to respond within that window is deemed approval.
Permitted sites over one acre must keep sediment discharge to five tons per acre per year, notify the department within 48 hours of starting work, and inspect the site weekly and after every half-inch rain event, filing written reports. The department can require a bond or letter of credit and may post a stop-work order or revoke the permit for noncompliance. Appeals go to the County Board of Adjustment, which charges a $500 application fee (Sec. 27-13).
Violations & Fines
A responsible party who disturbs land without a required permit, ignores an approved erosion control plan, or violates a stop-work order faces a forfeiture of not less than $100 nor more than $500 per offense under Sec. 27-12, plus prosecution costs; each day the violation continues is a separate offense. The county can also seek a cease-and-desist order or an injunction instead of, or in addition to, a forfeiture action.
Frequently Asked Questions
When does Fond du Lac County require an erosion control permit?
What happens if I start grading without a permit?
Are single-family homes exempt from the erosion ordinance?
How long is a Fond du Lac County erosion control permit valid?
Sources & Official References
Other rules in Fond du Lac County
Compare Fond du Lac County to another location·View the Wisconsin environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.