Key Facts

Permit trigger
5+ parcel split or 20,000 sq ft impervious add
Administering agency
County Land and Water Conservation Department
Maintenance agreement
Recorded with County Register of Deeds
Penalty
$100-$500 forfeiture per day
Appeal fee
$500 to County Board of Adjustment

Summary

New development in unincorporated Fond du Lac County that splits a parcel into five or more lots or adds 20,000 square feet or more of impervious surface must get a stormwater management permit under County Code Sec. 27-104. The Land and Water Conservation Department reviews the plan, and violators face a forfeiture of $100 to $500 per day under Sec. 27-113.

These county ordinances apply to unincorporated areas of Fond du Lac County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Unless otherwise exempt under section 27-104(1)(b), all stormwater management provisions of this chapter shall apply to all land developing activity that meet any of the following and a permit under section 27-108 shall be required:1.Divides an existing tax parcel into five separate parcels of, regardless of size, within a common plan of development;2.Ultimately results in the addition of impervious surfaces of 20,000 square feet or greater in total area, including smaller individual sites that are part of a common plan of development; or ... Any person, firm, association, or corporation ... who does not comply with the provisions of this chapter shall be subject to a forfeiture of not less than $100.00 or more than $500.00 per offense, together with the costs of prosecution. Each day that the violation exists shall constitute a separate offense.

Full Breakdown

County Code Chapter 27, Article II, adopted under Wis. 07(6), requires a stormwater management permit for post-construction land development in unincorporated Fond du Lac County that meets any trigger listed in Sec. 27-104(1)(a): dividing an existing parcel into five or more separate parcels within a common plan of development, adding 20,000 square feet or more of impervious surface (counting smaller phased sites together), or any other activity the Land and Water Conservation Department determines could significantly increase downstream flooding, erosion or pollution. 125), agricultural and silviculture nonpoint discharges, sites with less than ten percent connected impervious area totaling under an acre, and underground utility work.

Permit holders must record a maintenance agreement with the County Register of Deeds under Sec. 27-110 binding future owners to keep stormwater practices in working order, and the department can require a financial guarantee sized to cover construction and maintenance costs (Sec. 27-111). Fees are set by the County Land Conservation Committee (Sec. 27-112). Enforcement under Sec. 27-113 starts with certified-mail notice describing the violation and a correction schedule; the department can post a stop-work order, revoke the permit, or refer the matter for a cease-and-desist order, and noncompliance carries a forfeiture of $100 to $500 per offense with each day counted separately. Appeals of department decisions go to the County Board of Adjustment for a $500 application fee (Sec. 27-114).

Violations & Fines

Failing to obtain a required stormwater permit, or violating an approved stormwater management plan or maintenance agreement, is a forfeiture of not less than $100 nor more than $500 per offense under Sec. 27-113, with each day of noncompliance a separate violation, plus prosecution costs. The Land and Water Conservation Department can also post a stop-work order, revoke the permit, or seek an injunction instead of a forfeiture case.

Frequently Asked Questions

What triggers a stormwater permit in Fond du Lac County?
Under Sec. 27-104(1)(a), a permit is required when a project divides a parcel into five or more lots, adds 20,000 square feet or more of impervious surface (even across phased sites under one plan), or the Land and Water Conservation Department finds the activity could significantly increase downstream flooding or erosion in unincorporated Fond du Lac County.
Do small residential lots need a stormwater permit?
Generally no. Sec. 27-104(1)(b) exempts one- and two-family homes disturbing less than one acre outside a common development plan, and it exempts sites with less than ten percent connected impervious area where total impervious surface stays under one acre.
What is a stormwater maintenance agreement?
Sec. 27-110 requires permit holders to record a maintenance agreement with the County Register of Deeds that binds the property owner, and future owners, to inspect and maintain stormwater practices on a set schedule, with the Land and Water Conservation Department authorized to enter the property to check compliance.
What's the penalty for violating the stormwater ordinance?
Sec. 27-113 sets a forfeiture of $100 to $500 for each day a violation continues, on top of prosecution costs, and the county can also post a stop-work order, revoke the permit, or pursue an injunction against the responsible party.

Sources & Official References

Other rules in Fond du Lac County

All Fond du Lac County rules

Compare Fond du Lac County to another location·View the Wisconsin environmental rules overview

Get notified when Stormwater Management in Fond du Lac County, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.