Georgetown, KY Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- Soil disturbance of 5,000 square feet or greater
- Review time
- Five working days (Tier I), 20 working days (Tier II)
- Maximum cut and fill slope
- 2H:1V unless approved by the issuing authority
- Stabilization
- Seeding or mulching within 15 days of mass grading
- Soil stockpiles
- Stabilized at the end of each workday
- Violation class
- Class 2, initial fine $100.00
Summary
Georgetown requires a land disturbance permit before anyone disturbs 5,000 square feet or more of soil. Chapter 14, Article III ties each permit to a stormwater pollution prevention plan (SWPPP) reviewed by the Georgetown Stormwater Quality Division, sets slope, stabilization and inspection standards, and treats violations as Class 2 civil offenses under the code enforcement system.
(a) Land disturbance activity. ... (1) Any land disturbance activity that requires the disturbance of soil of 5,000 square feet or greater is subject to the provisions of this article and shall not take place without an authorized land disturbance permit. ... (c) At a minimum, the following requirements shall be met: (1) Cut and fill slopes shall be no greater than 2H:1V, unless approved by the issuing authority. (2) Clearing and grading, except that necessary to establish sediment control devices, shall not commence until sediment control devices have been installed. (3) Erosion control methods shall include the following: ... b. Soil stabilization by seeding/mulching within 15 days of mass grading operations for borrow (excavation) and fill areas; c. Stabilizing soil stockpiles at the end of each workday; ... (6) Prevention of mud and debris onto public roadways by construction equipment and vehicles shall include the installation of crushed stone construction entrances or an on-site tire washing station at the point of ingress and egress to the public roadway.
Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 4).
Full Breakdown
Article III of Chapter 14 (Erosion Prevention and Sediment Control) controls land disturbances, soil storage and the erosion and sedimentation that result. The issuing authority is the Georgetown Stormwater Quality Division (GSQUAD) and its designees (§ 14-62). Under § 14-63, a land disturbance permit is required for soil disturbance of 5,000 square feet or greater. A lot under one acre that is part of a larger common plan of development disturbing one acre or more is not exempt: the lot owner or homebuilder gets a separate permit, and the developer stays jointly responsible until the larger plan receives an approved KPDES notice of termination. Exemptions cover work under 5,000 square feet not in or near critical areas, cemetery graves, emergencies posing immediate danger to life or property, agricultural operations under an individual agriculture water quality plan, and usual and customary site investigations. They fall away if the issuing authority determines runoff from the work is creating erosion.
Every application includes a SWPPP (§ 14-65), submitted as a Tier I or Tier II plan. GSQUAD responds in writing within five working days of a complete application and Tier I SWPPP, or 20 working days for a Tier II SWPPP, and silence does not authorize anyone to proceed (§ 14-64).
Section 14-66 follows the Kentucky Erosion Prevention and Sediment Control Manual and Field Guide. Cut and fill slopes stay at 2H:1V or flatter unless approved. Clearing and grading cannot start until sediment control devices are installed. Sites greater than 30 acres phase their clearing, and measures must handle storm events up to and including a two-year, 24-hour event. Construction vehicles cannot track mud onto public roads, so crushed stone entrances or an on-site tire washing station are required, and maintenance is performed before the next storm event.
Under § 14-67 the permittee notifies the issuing authority 24 hours in advance of inspections, except routine or post-rainfall inspections, and keeps a report after each inspection at the job site. Permit fees follow a schedule on file in the clerk-treasurer's office (§ 14-69).
Violations & Fines
Violating Article III is a civil offense enforced under Chapter 2, Article VI by the code enforcement board and code enforcement officers, and § 14-68 classes every violation as Class 2. Under § 2-842 a Class 2 violation starts at $100.00, with another $100.00 added for each seven days unremedied until the total reaches $1,000.00. A code enforcement officer can issue a stop-work order (§ 2-843). Penalties are waived only if the same violation has not occurred on the property that calendar year and it is remedied within seven days.
Frequently Asked Questions
Do I need a Georgetown permit for a small grading project?
How long does GSQUAD take to review a land disturbance application?
What does Georgetown require at a construction site entrance?
How much is the fine for an erosion control violation?
Sources & Official References
Other rules in Georgetown
Compare Georgetown to another location·View the Kentucky environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.