Harrisburg, PA Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Governing section
Harrisburg Codified Ordinances § 9-905.1, erosion and sedimentation requirements
Required steps
BMPs, written plans, plan approval, E&S and NPDES permits, plans kept on site
Reviewing bodies
PADEP and Dauphin County Conservation District
Fill leveling deadline
Three months after placement under § 7-331.10(C)
Slope trigger
Natural slope over 25% across more than 1,000 square feet
Fine
Not more than $1,000 per violation, each day separate

Summary

In the City of Harrisburg, Pennsylvania, earth disturbance requires written erosion and sediment control plans, plan approval and NPDES permits under Codified Ordinances § 9-905.1, with proof of PADEP or Dauphin County Conservation District approval given to the City and the approved plan kept on site. Violations are a summary offense up to $1,000 per day.

A. The applicant shall meet requirements as contained in 25 Pa. Code, Chapters 92 and 102, as required, and applicable as follows: (1) The implementation and maintenance of erosion and sediment control BMPs. (2) Development of written plans. (3) Submission of plans for approval. (4) Obtaining erosion and sediment control and NPDES permits. (5) Maintaining plans and permits on site. B. Evidence of any necessary plan or permit approval for earth disturbance activities from PADEP or the Dauphin County Conservation District must be provided to the City of Harrisburg. C. A copy of the approved erosion and sediment control plan and any other permit, as required by PADEP or the Dauphin County Conservation District, shall be available at the project site at all times if required under 25 Pa. Code Chapter 102.

Full Breakdown

Chapter 9-905 of the Harrisburg Codified Ordinances, part of the stormwater management Part 9, sets the construction-phase rules. Section 9-905.1(A) requires the applicant to meet the requirements of 25 Pa. Code, Chapters 92 and 102, as required, including five steps: implementation and maintenance of erosion and sediment control BMPs, development of written plans, submission of plans for approval, obtaining erosion and sediment control and NPDES permits, and maintaining plans and permits on site.

Subsection (B) puts the paperwork duty on the applicant: evidence of any necessary plan or permit approval for earth disturbance activities from PADEP or the Dauphin County Conservation District must be provided to the City of Harrisburg. Subsection (C) requires a copy of the approved erosion and sediment control plan and any other required permit to be available at the project site at all times if required under 25 Pa. Code Chapter 102.

Temporary roadways, such as for utility construction or timber harvesting, must meet the erosion and sedimentation and stream crossing standards of 25 Pa. Code, Chapters 102 and 105, and the plan goes to the Dauphin County Conservation District for approval. It must address roadway design including haul roads and staging areas, runoff control structures, stream crossings, access to public roadways including a rock construction entrance for mud and debris control, and a remediation plan. Where infiltration BMPs are proposed, § 9-905.1(E) requires them to be protected from sedimentation, compaction and sediment-laden runoff during construction, with the protection identified, for example orange construction fence around the perimeter. Section 9-905.2 requires all regulated activities within the Paxton Creek watershed to conform to current TMDL requirements.

The zoning code adds its own layer. Section 7-331.10(A) conditions each City permit on full compliance with state erosion and sedimentation regulations, lets the Zoning Officer require an erosion and sedimentation control plan reviewed by the Dauphin County Conservation District wherever soil will be disturbed, and makes failure to comply cause for suspension of City permits. Under § 7-331.10(C), fill placed on a site must be leveled off and properly sloped within three months, except soil stockpile areas shown on an approved plan. Under § 7-331.5, building a new principal building or parking lot on natural slope over 25% across more than 1,000 square feet requires Zoning Officer and City Engineer review and a detailed soil erosion and sedimentation control plan.

Violations & Fines

Under § 9-921.5, violating Part 9 is a summary offense with a fine of not more than $1,000 for each violation, recoverable with costs, and each day is a separate offense. The Solicitor can seek injunctions or mandamus, a violation is a public nuisance under § 9-921.3, and approvals can be suspended or revoked under § 9-921.4. The Department of Public Works and City Engineer enforce, and appeals run to the City within 30 days.

Frequently Asked Questions

What erosion controls does Harrisburg require on a construction site?
Section 9-905.1(A) requires implementation and maintenance of erosion and sediment control BMPs, written plans, plan approval, erosion and sediment control and NPDES permits, and keeping plans and permits on site. The applicant must meet 25 Pa. Code, Chapters 92 and 102, as required.
Who approves the plan?
Evidence of any necessary plan or permit approval from PADEP or the Dauphin County Conservation District must be provided to the City of Harrisburg. Under § 7-331.10(A), the Zoning Officer can require a plan reviewed by the Dauphin County Conservation District wherever soil will be disturbed.
How long can fill sit unleveled on a Harrisburg site?
Section 7-331.10(C) requires fill placed on a site to be leveled off and properly sloped within three months of placement. The exception is a soil stockpile area shown on an approved erosion and sedimentation control plan.
What is the penalty for an erosion violation?
Under § 9-921.5, a violation of the stormwater Part 9 is a summary offense with a fine of not more than $1,000 for each violation, recoverable with costs. Each day the violation continues is a separate offense, and the City can also seek injunctions through its Solicitor.

Sources & Official References

Other rules in Harrisburg

All Harrisburg rules

Compare Harrisburg to another location·View the Pennsylvania environmental rules overview

Get notified when Erosion Control in Harrisburg, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.