Harrisburg, PA Environmental Rules: Stormwater Management (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Governing section
Harrisburg Codified Ordinances § 9-903.1
Core requirement
Approved SWM site plan before any regulated activity starts
Maximum fine
$1,000 per violation, each day separate (§ 9-921.5)
Watercourse easement
Minimum width of 20 feet
Enforcers
Department of Public Works and the City Engineer
Appeal window
30 days to the City, 30 days to Dauphin County court

Summary

In the City of Harrisburg, Pennsylvania, regulated activities need an approved stormwater management (SWM) site plan before work begins, and the plan must show capacity for volume and rate control. Violations are summary offenses with fines up to $1,000 per violation per day.

§ 9-903.1. General requirements. A. For all regulated activities, unless specifically exempted in § 9-903.2: (1) Preparation and implementation of an approved SWM site plan is required. (2) No regulated activities shall commence until the City of Harrisburg issues written approval of a SWM site plan, which demonstrates compliance with the requirements of this Part 9. (3) The SWM site plan shall demonstrate that adequate capacity will be provided to meet the volume and rate control requirements, as described under §§ 9-903.3 and 9-903.4 of this Part 9. (4) The SWM site plan approved by the City of Harrisburg shall be on site throughout the duration of the regulated activities.

Full Breakdown

Chapter 9-903 of the Harrisburg Codified Ordinances, adopted 5-14-2013 as Ord. No. 6-2013, is the stormwater management chapter for the City of Harrisburg. Section 9-903.1(A) requires, for all regulated activities not specifically exempted in Section 9-903.2, preparation and implementation of an approved SWM site plan. No regulated activity shall commence until the City issues written approval of the plan. The plan must demonstrate adequate capacity to meet the volume and rate control requirements of Sections 9-903.3 and 9-903.4, and the approved plan must be on site throughout the regulated activities.

Earth disturbance adds erosion and sediment control best management practices (BMPs) designed to meet Title 25 of the Pennsylvania Code, including Chapter 102, and the Clean Streams Law. Impervious area is measured across the whole proposed development, even if built in stages. Where diffused flow is concentrated and discharged onto adjacent property, the applicant must document adequate downstream conveyance and provide an executed easement. Where watercourses cross a site, drainage easements with a minimum width of 20 feet are required. Roof drains shall not be connected to streets, sanitary or storm sewers, or roadside ditches, though the City can permit a direct connection case by case.

Chapter 9-913 bans illicit discharges. Under Section 9-913.1, any drain or conveyance that lets a nonstormwater discharge, including sewage, process wastewater and wash water, enter the City's separate storm sewer system or waters of the commonwealth is prohibited. Listed exceptions include firefighting discharges, lawn watering, uncontaminated groundwater, dechlorinated swimming pool discharges and water from individual residential car washing, unless found to be significant contributors to pollution. Section 9-913.3 bars altering any existing stormwater BMP without written City approval.

The Department of Public Works and the City Engineer enforce the chapter under Section 9-921.2. Appeals go to the City within 30 days of its action, then to the Dauphin County Court of Common Pleas within 30 days of the decision, under Section 9-921.6.

Violations & Fines

Under Section 9-921.5, violating the stormwater chapter is a summary offense carrying a fine of not more than $1,000 for each violation, recoverable with costs, and each day is a separate offense with cumulative penalties. Section 9-921.3 deems any violation a public nuisance, Section 9-921.4 allows suspension or revocation of approvals, and the Solicitor can seek injunctions.

Frequently Asked Questions

Do I need approval before doing stormwater work in the City of Harrisburg?
Yes, for regulated activities not exempted under Section 9-903.2. Section 9-903.1(A) says no regulated activities shall commence until the City of Harrisburg issues written approval of a SWM site plan showing compliance with Part 9.
Can I send wash water or sewage into a storm drain?
No. Section 9-913.1 prohibits any drain or conveyance that lets nonstormwater discharge, including sewage, process wastewater and wash water, enter the City's separate storm sewer system. Listed exceptions include lawn watering and water from individual residential car washing.
Can I connect my roof drain to the street or sewer?
Section 9-903.1(R) says roof drains shall not be connected to streets, sanitary or storm sewers, or roadside ditches. When a direct connection is more advantageous, the City of Harrisburg permits it on a case-by-case basis. Section 9-913.2 directs roof drains to infiltration areas or vegetative BMPs.
What is the fine for violating the stormwater rules?
Section 9-921.5 makes a violation a summary offense with a fine of not more than $1,000 for each violation, recoverable with costs. Each day the violation continues is a separate offense. Appeals run 30 days to the City and then 30 days to the Dauphin County Court of Common Pleas.

Sources & Official References

Other rules in Harrisburg

All Harrisburg rules

Compare Harrisburg to another location·View the Pennsylvania environmental rules overview

Get notified when Stormwater Management in Harrisburg, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.