Skip to main content
CityRuleLookup

Hudson, NH Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Stabilization deadline
5 days if idle over 30 days
Final-grade stabilization
Within 3 days
First-offense penalty
$275 per day
Repeat-offense penalty
$550 per day
Pre-construction step
Meeting with Town Engineer required
Enforcing office
Town Engineer / Planning Board

Summary

In the Town of Hudson, New Hampshire, any site subject to Site Plan Review or Subdivision Regulations must follow Section 290-6's construction erosion control standards: disturbed soil idle more than 30 days must be stabilized within 5 days, final-graded areas within 3 days, and a pre-construction meeting with the Town Engineer is required before earth moving starts.

§ 290-6. Construction Erosion Control and Stormwater Standards. The design shall conform to the standards set forth in NHDES NH Stormwater Manual (as amended), or as directed in the Land Use Regulations, whichever dictates the higher standard. ... Disturbed soil areas that will remain idle for more than 30 days shall be temporarily stabilized as soon as practicable but no later than five days from the initial disturbance with seed and mulch, erosion control blankets or crushed stone or other suitable measures approved by the TOWN ENGINEER or designated representative. All disturbed soil areas that have achieved final grading shall be permanently stabilized within three days following final grading. ... shall be subject to a civil penalty of $275 for the first offense, and $550 for subsequent offenses, for each day that such violation is found to continue after the conviction date or after the date on which the violator receives written notice from the municipality that the violator is in violation, whichever is earlier.

Full Breakdown

Chapter 290, Stormwater Management, sets Hudson's construction-phase erosion rules in Section 290-6, which requires every project's Stormwater Management and Erosion Control Plan (SMECP) to meet, at minimum, the Best Management Practice guidance in the state's NH Stormwater Management Manual. Subsection A lists specific field requirements: natural vegetation must be retained and protected wherever practical, with vegetated areas to be preserved marked off by construction fencing; soil disturbance is barred within the buffer setbacks of the Town's Wetland and Conservation Overlay District; and construction stone access pads must be installed at every site entrance and exit to keep mud off pavement. A pre-construction meeting with the Town Engineer or a designated representative is required before earth-moving activity begins, and it must happen only after perimeter erosion controls, protective fencing, waste disposal and access pads are already in place.

The chapter's timing rule is exact: disturbed soil that will sit idle for more than 30 days must be temporarily stabilized, with seed and mulch, erosion control blankets, crushed stone or another approved measure, no later than five days after the initial disturbance, and any area that reaches final grading must be permanently stabilized within three days. Areas left idle over winter need separate winter stabilization measures from the NH Stormwater Manual, Volume 3. All erosion and sediment control measures must be routinely inspected and maintained by a qualified professional until the site is fully stabilized, after which the temporary measures and any accumulated sediment must be removed.

Enforcement runs through Section 290-12: a written Notice of Violation or Cease and Desist Order issued by the Town Engineer sets a deadline to correct the problem, and a violation that continues carries a civil penalty of $275 for a first offense and $550 for each subsequent offense, per day the violation continues after notice.

Violations & Fines

A Notice of Violation or Cease and Desist Order from the Town Engineer under Section 290-12 gives the property owner a deadline to fix an erosion-control problem. A violation that continues past that deadline carries a civil penalty of $275 for the first offense and $550 for each offense after, charged separately for every day it continues, plus the Town's litigation costs and attorney's fees if it sues to enforce the order.

Frequently Asked Questions

How long can disturbed soil sit exposed on a Hudson construction site?
Under Section 290-6A(9), soil that will remain idle for more than 30 days must be temporarily stabilized, using seed and mulch, erosion control blankets, crushed stone or another Town Engineer-approved method, no later than five days after the ground was first disturbed. Once an area reaches final grading, it must be permanently stabilized within three days.
What happens before I can start moving earth on a project?
Section 290-6A(8) requires an on-site pre-construction meeting with the Town Engineer or a designated representative before earth-moving activities begin, and that meeting can only happen after perimeter erosion controls, protective fencing, waste disposal facilities and construction stone access pads are already installed at the site.
What is the fine for an erosion-control violation in Hudson?
Section 290-12B sets a civil penalty of $275 for a first offense and $550 for each offense after that, with every day a violation continues after written notice counting as a separate offense. The Town Engineer issues a written Notice of Violation or Cease and Desist Order first, giving the owner a chance to correct it.

Sources & Official References

Other rules in Hudson

All Hudson rules

Compare Hudson to another location·View the New Hampshire environmental rules overview

Get notified when Erosion Control in Hudson, NH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in this county handle erosion control.

Nashua, NH
Some Restrictions