Jonesboro, AR Environmental Rules: Erosion Control (2026)
Key Facts
- Disturbance trigger
- 1 acre or more of land
- Common-plan trigger
- Applies if larger plan tops 1 acre
- Permit required
- Grading permit + SWPPP
- Pre-work inspection
- Confirms erosion controls installed
- Daily fine range
- $100.00-$500.00 per day
Summary
Jonesboro requires a Stormwater Pollution Prevention Plan and grading permit before disturbing one acre or more of land for construction, or less than an acre if it is part of a larger project that will ultimately exceed one acre. The city engineer must issue the permit before land-disturbing work starts.
Any person, firm, corporation, business, or legal entity proposing to disturb for construction purposes (e.g., clear, grade, excavate, etc.) one acre or more of total land area, or less than one acre of total land area that is part of a larger common development or sale if the larger common plan will ultimately disturb one acre or more, shall prepare and submit a SWPPP to the city engineer for review and be issued a grading permit prior to commencement of the proposed land disturbance activities.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 16).
Full Breakdown
Sec. 112-8 requires any person, firm, corporation, business, or legal entity proposing to clear, grade, excavate, or otherwise disturb one acre or more of total land area for construction purposes to prepare and submit a SWPPP to the city engineer for review and obtain a grading permit before commencing the land disturbance. The one-acre threshold also captures smaller sites that are part of a larger common development or sale where the overall plan will ultimately disturb an acre or more, closing the obvious loophole of phasing a project into sub-acre parcels.
Sec. 112-11(b)(3) places an ongoing duty on developers to provide, install, and maintain appropriate erosion control measures and other stormwater best management practices, both during and after construction, to minimize adverse impacts to water quality or the local environment. Sec. 112-43(a)(2)(a) requires the city engineer to inspect the site prior to the initiation of the project, specifically to confirm temporary or permanent erosion prevention and sediment control practices have been installed, and again after rough grading and upon project completion. Compliance with a valid NPDES construction permit is treated as compliance with the local SWPPP requirement under Sec. 112-12(g), tying the local erosion rule directly to the state/federal permit.
Violations & Fines
Disturbing an acre or more without the required grading permit and SWPPP violates Sec. 112-8 and is subject to the Sec. 112-2 penalty of $100.00 to $500.00 per day, each day a separate offense. The city engineer may issue a stop work order under Sec. 112-44(b) when erosion control provisions are violated, served on the developer and posted at the site; an appeal must be filed with the stormwater management board within 30 days or the stop work order stays in effect.
Frequently Asked Questions
When does Jonesboro require an erosion control plan?
Who issues the grading permit in Jonesboro?
Does an NPDES permit satisfy Jonesboro's erosion rule?
Sources & Official References
Other rules in Jonesboro
Compare Jonesboro to another location·View the Arkansas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.