Key Facts

Governing section
Code of Ordinances Sec. 112-129(f)
Certificate form
FEMA Form 086-0-33
Who certifies
State-registered engineer or land surveyor
Certificate stages
Drawings, framing, finished construction
Review timeline
City engineer reviews permits in 15 business days
Penalty
$100-$500 per day, misdemeanor

Summary

Any lot in a local or FEMA-mapped special flood hazard area must show the effective base flood elevation on the record plat, and a state-registered professional engineer must set the lowest floor elevation. Compliance is proven with a FEMA elevation certificate submitted at three separate construction stages under Code of Ordinances Sec. 112-129(f).

(f)Floor elevations.(1)Any proposed lot or lots located in a local or FEMA special flood hazard area (SFHA) shall be identified as such on the record plat along with the effective base flood elevation (BFE).(2)The designed lowest floor of any structure to be located in a local or FEMA designated SFHA shall be established by a professional engineer registered in the state, using good engineering practice.(3)An elevation certificate (FEMA Form 086-0-33) shall be used to certify the elevation of any structure to be constructed in local or FEMA designated SFHA. Certificates may be prepared and sealed by either a professional engineer or a land surveyor provided that person is registered in the state. An elevation certificate must be prepared, submitted, and approved at the following times... a.Construction drawings: Before a building permit is issued for the anticipated construction activity;b.Building under construction: Before the framing of any building wall system... andc.Finished construction: Prior to issuance of certificate of occupancy and only after all construction has been completed.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 16).

Full Breakdown

Jonesboro's stormwater management chapter requires that any lot proposed inside a local or FEMA-designated special flood hazard area (SFHA) be identified as such on the record plat, along with the effective base flood elevation (BFE), per Sec. 112-129(f)(1). The designed lowest floor of any structure built in the SFHA must be established by a professional engineer registered in Arkansas using good engineering practice, Sec. 112-129(f)(2). Compliance is documented on FEMA Form 086-0-33, the elevation certificate, which may be prepared and sealed by either a registered professional engineer or a registered land surveyor, Sec.

112-129(f)(3). The certificate must be prepared, submitted, and approved at three points in construction: with the construction drawings before a building permit is issued, again before the framing of any building wall system, and a final certificate after all construction is complete and before a certificate of occupancy is issued. Builders in the SFHA also fall under the floodplain development permit process at Sec. 112-107, requiring submission of the application and supporting documentation to the city planning office, which forwards it to the city engineer for review within 15 business days of receipt; a missed deadline is not deemed approval.

Sanitary sewer manholes located in a floodplain must carry either a watertight cover or a rim elevation at least one foot above the base flood's high water elevation, per Sec. 112-129(e). Failing to comply with the stormwater and floodplain regulations is a misdemeanor under Sec. 00 per day, with each day of noncompliance treated as a separate offense.

Violations & Fines

Building in the SFHA without the required elevation certificate, or without engineer-certified lowest floor elevations, blocks issuance of a certificate of occupancy under Sec. 112-160(b). Any violation of the stormwater/floodplain regulations under Chapter 112 is a misdemeanor carrying a fine of $100.00 to $500.00 per day under Sec. 112-187, with each day a separate offense referred by the city engineer or chief building official to the city attorney.

Frequently Asked Questions

Who has to file an elevation certificate in Jonesboro?
Anyone constructing a structure on a lot in a local or FEMA-designated special flood hazard area must file a FEMA elevation certificate (Form 086-0-33) prepared by a state-registered engineer or land surveyor, per Sec. 112-129(f)(3) of the Code of Ordinances.
When during construction is the certificate required?
Three times: with the construction drawings before the building permit is issued, before framing of any building wall system, and a final certificate after construction is complete and before a certificate of occupancy is issued, per Sec. 112-129(f)(3).
Who reviews a floodplain development permit application?
The city planning office forwards the application to the city engineer, who must review and comment on or approve it within 15 business days of receipt; missing that deadline is not treated as approval, per Sec. 112-107.
What happens if I skip the elevation certificate?
The city will not issue a certificate of occupancy until the registered engineer or surveyor submits certification of the lowest floor elevation on a FEMA elevation certificate, per Sec. 112-160(b), and violations of Chapter 112 carry fines of $100.00 to $500.00 per day under Sec. 112-187.

Sources & Official References

Other rules in Jonesboro

All Jonesboro rules

Compare Jonesboro to another location·View the Arkansas environmental rules overview

Get notified when Flood Elevation Requirements in Jonesboro, AR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.