Key Facts

Permit authority
Director of Public Works
Governing chapter
LVMC Chapter 20.08
Required for
grading, filling, excavation, drainage work
Max fine (unpermitted work)
$1,000 plus possible jail
Design standard
Hydrologic Criteria & Drainage Design Manual

Summary

The City requires a development permit from the Director of Public Works before any grading, filling, or construction that alters drainage on a property.

...it shall be unlawful for any person to begin any construction or development on any land within the City without first obtaining a development permit from the Director of Public Works. Application for a development permit shall be made on forms furnished by the Director of Public Works and may include, but not be limited to, plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in question; existing or proposed structures, fill, storage of materials, drainage facilities; debris control structures...

Source: Clark County Public Works — Development Review (drainage & grading)View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 61).

Full Breakdown

Before grading, filling, excavating, or building anywhere in the city, you need a development permit from the Director of Public Works under LVMC 20.08.130. The application has to show existing and proposed structures, fill, drainage facilities, and debris control structures on scaled plans, plus documentation that the work complies with the Flood Control Master Plan and the Hydrologic Criteria and Drainage Design Manual. "Development" is defined broadly in LVMC 20.08.050 to include mining, dredging, filling, grading, paving, and excavation, so routine yard regrading or drainage work on a lot triggers the same permit as larger site work. The Director can fold this review into a building-permit application instead of a stand-alone permit, but the underlying plan and drainage documentation requirements still apply.

Violations & Fines

Grading or altering drainage without the required development permit is a Code violation. Under the citywide general penalty (LVMC 1.24.010), an unpermitted violation is punishable by a fine of up to $1,000, up to six months in jail, or both, and LVMC 1.24.020 makes each day the violation continues a separate offense.

Frequently Asked Questions

Do I need a permit just to regrade my yard for drainage?
Yes. LVMC 20.08.050 defines "development" to include grading and filling, so a development permit from the Director of Public Works applies under LVMC 20.08.130.
What has to be in the permit application?
Scaled plans showing structures, fill, drainage facilities, and debris control structures, plus documentation showing compliance with the Flood Control Master Plan and Drainage Design Manual per LVMC 20.08.130(A).
Can this be handled through my building permit instead?
Yes, if the Director allows it. LVMC 20.08.130(B) lets the drainage review be folded into another permit process, like a building permit, as long as the same information is submitted.

Sources & Official References

Other rules in Las Vegas

All Las Vegas rules

Compare Las Vegas to another location·View the Nevada environmental rules overview

Get notified when Erosion Control in Las Vegas, NV changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Clark County handle erosion control.

North Las Vegas, NV
Some Restrictions
Henderson, NV
Some Restrictions