Mason County, WA Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger
- 2,000+ sq ft new impervious surface or under 1 acre disturbed
- Dry season limit
- Bare soil exposed no more than 7 days (May-Sept)
- Wet season limit
- Bare soil exposed no more than 2 days (Oct-Apr)
- Access route
- Construction access limited to one stabilized route
- Larger projects
- 5,000+ sq ft or 1+ acre needs PSQC plan
- Enforcement
- Misdemeanor, up to $500 fine or 90 days jail
Summary
In unincorporated Mason County, any new construction adding 2,000 square feet or more of impervious surface, or disturbing under an acre, must follow the small parcel erosion and sediment control standards in MCC 14.48.140. Builders must limit vehicle access to one stabilized route, keep bare soil covered, and file a small parcel erosion and sediment control plan with Community Development before grading begins.
The following new development shall be required to control erosion and sediment during construction, to permanently stabilize soil exposed during construction, to comply with small parcel requirements 1 through 4, to prepare a small parcel erosion and sediment control plan : ... (a) creation or addition of less than two thousand square feet of impervious surface area; (b) land disturbing activities of less than one acre. (1)Small Parcel Requirement #1 Construction Access Route. Construction vehicle access shall be, whenever possible, limited to one route. Access points shall be stabilized to minimize the tracking of sediment onto public roads. ... (2)Small Parcel Requirement #2 Stabilization of Potentially Erodible Denuded Areas. Soil stabilization. All exposed and unworked soils with erosion potential shall be stabilized by suitable application of BMPs, including but not limited to sod or other vegetation, plastic covering, mulching, or application of ground base on areas to be paved. ... From October 1 through April 30, no soils shall remain exposed for more than two days. From May 1 through September 30, no soils shall remain exposed for more than seven days.
Full Breakdown
Mason County Code Chapter 14.48, the county's stormwater and drainage ordinance, requires every construction project in unincorporated Mason County that adds at least 2,000 square feet of new impervious surface, or disturbs land, to control erosion during and after work under MCC 14.48.140. Projects under one acre of disturbance qualify as "small parcel" work and must satisfy five numbered requirements. Requirement #1 limits construction vehicle access to a single stabilized route so mud is not tracked onto county roads, and any sediment that reaches pavement must be shoveled or swept clean immediately and again at day's end; hosing it away is allowed only after the sediment itself is removed.
Requirement #2 sets a calendar-based soil exposure limit: bare, worked ground cannot sit uncovered for more than two days between October 1 and April 30, the wet season, or more than seven days from May 1 through September 30, and it must be stabilized with sod, mulch, plastic sheeting or a gravel base in the meantime. Requirement #3 requires vegetative buffers, silt fencing, dikes or filters to keep sediment off neighboring parcels, and Requirement #4 makes the property owner responsible for inspecting and maintaining every BMP for as long as it functions.
A small parcel erosion and sediment control plan documenting these measures must be submitted to Mason County Community Development and, per MCC 14.48.150, is required for any single-family residence or duplex adding 2,000 square feet or more of impermeable surface. Nonresidential work of 5,000 square feet or more, or disturbance of a full acre, escalates the requirement to a large parcel ESC plan and a permanent stormwater quality control (PSQC) plan stamped by a Washington-licensed civil engineer. Mason County Public Works can provide guidance on the accompanying drainage plan or sketch when one is needed.
Violations & Fines
Mason County Code § 1.04.010 makes any violation of the county's ordinances, including the Chapter 14.48 erosion and sediment control standards, a misdemeanor punishable by a fine of up to $500, up to 90 days in jail, or both. Each day an uncorrected violation continues, such as bare soil left exposed past the two- or seven-day limit, counts as a separate offense, and Community Development or Public Works can require additional erosion control measures during and after construction.
Frequently Asked Questions
Does a small home addition in unincorporated Mason County need an erosion control plan?
How long can bare dirt sit exposed on a Mason County construction site?
What happens if sediment tracks onto a public road from a Mason County job site?
Sources & Official References
Other rules in Mason County
Compare Mason County to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.