Skip to main content
CityRuleLookup

Medina, OH Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing chapter
Codified Ordinances Ch. 1349
Bond, single-family lot
$1,500
Bond, subdivisions
$1,500 per acre
2nd violation fee
$500 administrative fee
3rd+ violation fee
$1,000 administrative fee
Max misdemeanor penalty
$500 fine, 60 days jail

Summary

Medina requires an approved Stormwater Pollution Prevention Plan before soil-disturbing construction begins, backed by a $1,500 bond, stop-work orders and escalating fines up to $1,000, with a misdemeanor penalty of up to $500 and 60 days in jail under Chapter 1349.

The purpose of this regulation is to establish technically feasible and economically reasonable standards to achieve a level of erosion and sediment control that will minimize damage to property and degradation of water resources, and will promote and maintain the health and safety of the citizens of City of Medina ... This regulation applies to all parcels used or being developed, either wholly or partially, for new or relocated projects involving highways, underground cables, or pipelines; subdivisions or larger common plans of development; industrial, commercial, institutional, or residential projects; building activities on farms; redevelopment activities; general clearing.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025-01: Local legislation current through June 24, 2025 | State legislation current through December 31, 2024).

Full Breakdown

Chapter 1349, Erosion and Sediment Control, is Medina's separate construction-phase companion to the Chapter 1347 stormwater code. 01 applies the regulation to parcels developed for highways, underground cables or pipelines, subdivisions, industrial, commercial, institutional or residential projects, farm building activities and general clearing, exempting only activities covered by the Ohio Agricultural Sediment Pollution Abatement Rules. 12(c) bars any covered project from starting without an approved SWP3 or Abbreviated SWP3. 13 lets the City of Medina and the Medina County Soil and Water Conservation District issue immediate stop-work orders and conduct external inspections.

13(e) sets a graduated penalty scale for failing to maintain erosion controls: a first violation draws a Notice of Deficiency with three days to correct; a second violation adds a $500 administrative fee against the SWP3 bond; a third or subsequent violation triggers a Stop Work Order plus a $1,000 administrative fee against the bond. 14 lets the City Engineer suspend soil-disturbing activity for up to ninety days on notice. 99 makes any violation a third-degree misdemeanor punishable by a fine of not more than $500 or imprisonment of not more than sixty days, or both, with each day of continued noncompliance a separate offense. 04 was repealed by Ordinance 96-25 on May 12, 2025, when this standalone Chapter 1349 replaced it.

Violations & Fines

Starting soil-disturbing work without an approved SWP3, or failing to repair erosion and sediment controls per the approved plan, escalates under Section 1349.13(e): a Notice of Deficiency on the first violation, a $500 administrative fee against the bond on the second, and a $1,000 fee plus a Stop Work Order on the third. Section 1349.99 also makes any violation a third-degree misdemeanor punishable by up to $500 and sixty days in jail, each day a separate offense.

Frequently Asked Questions

Does Medina require an erosion control plan before construction?
Yes. Chapter 1349 requires an approved Stormwater Pollution Prevention Plan (SWP3) or Abbreviated SWP3 before soil-disturbing activity begins on covered projects, per Section 1349.12(c), backed by a bond of $1,500 for a single lot or $1,500 per acre for subdivisions.
What happens on a repeat erosion control violation in Medina?
Section 1349.13(e) escalates penalties: the first violation gets a Notice of Deficiency with three days to fix it, the second adds a $500 administrative fee against the bond, and the third or later violation triggers a Stop Work Order plus a $1,000 fee against the bond.
Who enforces Medina's erosion and sediment control rules?
Section 1349.13 gives enforcement authority to the City of Medina and the Medina County Soil and Water Conservation District, including the power to issue immediate stop-work orders and conduct external site inspections for compliance with the approved plan.

Sources & Official References

Other rules in Medina

All Medina rules

Compare Medina to another location·View the Ohio environmental rules overview

Get notified when Erosion Control in Medina, OH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.