O'Fallon, MO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
City Code § 405.245
Adopted by
Ordinance No. 7138, 9-26-2024
Design storm minimum
15-year, 20-minute storm
Post-storm cleanup deadline
24 hours after storm ends
Large-site runoff cap
2-yr/24-hr pre-development rate on 3+ acres
Enforcing official
City Director of Engineering

Summary

O'Fallon requires a Stormwater Pollution Prevention Plan (SWPPP) with engineered erosion and sediment controls before any major land disturbance begins. The rule, enacted by Ordinance No. 7138 in September 2024, sets design storm standards and cleanup deadlines enforced by the Director of Engineering.

This Section specifies or authorizes performance and design standards for a Stormwater Pollution Prevention Plan (SWPPP) to reduce the amount of sediment and other pollutants in stormwater discharges associated with the land disturbance activities... All erosion and sediment control measures shall be fully installed and implemented prior to any work necessitating major land disturbance so as to prevent the flow or runoff of mud, silt, dirt, debris and other materials onto streets, sidewalks and other public rights-of-way. Additionally, positive steps shall be exercised to prevent mud, silt, dirt, debris and other materials from damaging adjacent property and silting up all storm drainage systems whether on- or off-site. For storms exceeding the design storm (fifteen-year, twenty-minutes), any silt or debris leaving the site and affecting public rights-of-way or stormwater drainage facilities shall be cleaned up within twenty-four (24) hours after the end of the storm.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4860992; v58 updated 2026-05-14; through 05-14-2026).

Full Breakdown

), the Federal Water Control Act, and the Missouri Department of Natural Resources' State Operating Permit MO-R100A (or MO-R109 in a valuable water resource area). All erosion and sediment control measures must be fully installed before any major land-disturbing work begins, so mud, silt, dirt and debris do not run onto streets, sidewalks, rights-of-way or adjacent property, or silt up storm drainage systems on- or off-site. Runoff into receiving streams from land disturbance areas greater than three acres cannot exceed the two-year, twenty-four-hour peak runoff rate for that area's pre-developed state, and temporary discharges cannot accelerate erosion of a receiving stream's channel.

Controls and temporary facilities must be designed, at a minimum, to accommodate stormwater flows from a fifteen-year, twenty-minute design storm, using the Rational Method and the runoff coefficients set out in the code's Table 1 for the specific ground cover involved. If controls installed under an approved plan fail to meet these performance standards, the Director of Engineering or a designee may require the permittee to submit modified plans. SWPPPs must otherwise follow the Missouri Department of Natural Resources' Protecting Water Quality Field Guide, latest edition, for design criteria such as sediment trap, sediment basin and silt fence sizing and structural life limits.

Violations & Fines

For storms that exceed the fifteen-year, twenty-minute design storm, any silt or debris that leaves the site and reaches public rights-of-way or stormwater drainage facilities must be cleaned up within twenty-four hours after the storm ends. The Director of Engineering can order a permittee to resubmit and rebuild controls that are not performing to the code's standards, and City enforcement follows the procedures set out elsewhere in Section 405.245 for SWPPP violations.

Frequently Asked Questions

Does O'Fallon require a stormwater plan before construction starts?
Yes. Section 405.245 requires erosion and sediment control measures to be fully installed and implemented before any work causing major land disturbance begins, so mud, silt and debris cannot reach streets, sidewalks, rights-of-way or storm drains.
What design standard do O'Fallon's erosion controls have to meet?
Controls and temporary facilities must be sized to handle at least a fifteen-year, twenty-minute design storm, calculated with the Rational Method using the runoff coefficients in the code's Table 1 for the site's specific ground cover.
Who enforces O'Fallon's erosion control requirements?
The City's Director of Engineering or a designee reviews SWPPPs and can require a permittee to submit modified plans if installed controls fail to meet the performance standards in Section 405.245.
How fast must a builder clean up sediment that escapes the site during a big storm?
For storms exceeding the fifteen-year, twenty-minute design storm, any silt or debris that leaves the site and affects public rights-of-way or stormwater drainage facilities must be cleaned up within twenty-four hours after the storm ends.

Sources & Official References

Other rules in O'Fallon

All O'Fallon rules

Compare O'Fallon to another location·View the Missouri environmental rules overview

Get notified when Erosion Control in O'Fallon, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.