Parker, CO Environmental Rules: Erosion Control (2026)
Key Facts
- Permit required for
- Any grading, compaction, filling or earth movement
- Enforcing office
- Engineering Department
- Small-site security
- $2,500 plus CBMP costs, under 1 acre
- Large-site security
- $5,000 minimum, $2,000-$5,000/acre
- Permit term
- 24 months, renewable
- Plan review timeline
- 20 working days
Summary
The Town of Parker requires a grading permit from the Engineering Department before any grading or earth movement, specifically to minimize soil erosion and sediment movement under Chapter 11.10. Applicants must submit Construction Best Management Practice plans and post cash or letter-of-credit security tied to site size.
This Chapter provides a mechanism within the Town for the issuance of permits relating to grading and earth movement. Its purpose is to minimize soil erosion and movement of sediment, and to protect the water quality and soil surfaces during and after construction. ... (a)Unless specified in Section 11.10.060 below, no person, corporation, firm or entity shall commence grading and earth movement activities without first obtaining a permit. No permit shall be issued by the Engineering Department for any project until the provisions of this Chapter are satisfied and the real property that is the subject of the permit has received final site plan or subdivision plat approval in accordance with the Parker Land Development Ordinance, except as otherwise provided in Section 11.10.160 of this Chapter.
Full Breakdown
Chapter 11.10, Grading and Earth Movement, states its purpose is to minimize soil erosion and sediment movement and protect water quality during and after construction (Section 11.10.010). Section 11.10.030 bars grading or earth movement without a permit from the Engineering Department, and no permit issues until the property has final site plan or subdivision plat approval under the Parker Land Development Ordinance. Plans must meet the Town's Storm Drainage and Environmental Criteria Manual standards (Section 11.10.040) and be reviewed within twenty working days (Section 11.10.070).
Permits run twenty-four months (Section 11.10.080) and require a nonrefundable fee set by Town Council resolution (Section 11.10.090). Section 11.10.100 requires revegetation security: $2,500 plus construction site runoff control costs for sites under one acre, and a $5,000 minimum, calculated at $2,000 per acre for developable land or $5,000 per acre for nondevelopable land, for larger sites. Security is not released until perennial vegetation reaches at least 70% of pre-disturbance density, erosion is insignificant, weeds are held under 50% of total vegetation, and all Construction Best Management Practices are removed.
A grading exception exists for disturbances under one acre that the Engineering Department finds will not significantly affect neighboring property, but not where the parcel is part of a larger common development plan (Section 11.10.060). Noncompliance can trigger a stop-work order and withholding of building permits and certificates of occupancy under Section 11.10.120.
Violations & Fines
The Engineering Department may issue a notice of intent to stop work if an approved grading plan is not followed, and if the deviation is not corrected within the notice period, a stop work order follows under Section 11.10.120. Significant deviations can result in immediate stop-work action, withholding of building permits and certificates of occupancy, an added reinstatement fee, and forfeiture of the posted revegetation or CBMP security until the site is brought into compliance.
Frequently Asked Questions
Do I need a permit before grading a construction site in Parker?
How much security does Parker require for erosion control?
Is any grading exempt from Parker's permit requirement?
Sources & Official References
Other rules in Parker
Compare Parker to another location·View the Colorado environmental rules overview