Revere, MA Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger threshold
- Grade/vegetation change over 2,500 sq ft or 25% lot
- Fill storage trigger
- Over 100 cubic yards excavated material or fill
- Plan reviewer
- Department of Public Works
- Review deadline
- 90 calendar days to approve or deny
- Inspection notice
- 2 working days before key construction phases
- Enforcement tool
- Stop-work order until violation corrected
Summary
Revere requires an approved erosion and sediment control plan before any land-disturbing construction activity crosses set thresholds, under Municipal Code § 13.10.020. Grading or clearing more than 2,500 square feet (or 25% of the lot) or storing over 100 cubic yards of fill triggers the requirement, reviewed by the Department of Public Works.
No person shall excavate, cut, grade or perform any land-disturbing activities of significance, without an approved erosion and sediment control plan. Activities of significance are those which meet or exceed the following thresholds: a. Any change of existing grade of more than two thousand five hundred square feet or twenty-five percent of the lot whichever is smaller; ... In the event that the activity at a site violates the conditions as stated or shown on the approved erosion and sediment control plan in such a manner as to adversely affect the environment, public welfare/health and municipal facilities, then the superintendent of public works or director of municipal inspections may suspend work until the violations are corrected.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4804778; v14 updated 2026-05-04).
Full Breakdown
020 requires an approved erosion and sediment control plan before anyone excavates, cuts, grades, or otherwise disturbs land at a scale the ordinance calls 'significant': a grade change or vegetation removal of more than 2,500 square feet or 25% of the lot (whichever is smaller), storage of more than 100 cubic yards of excavated material or fill, or any disturbance under 2,500 square feet that's part of a larger common development or sale disturbing an acre or more. Emergency work and existing permitted nursery or agricultural operations are exempt.
Projects disturbing less than 20,000 square feet or storing 100 to 1,300 cubic yards count as 'minor' and need a plan showing property lines, existing and proposed structures and impervious surface, stormwater utilities, and control measures; larger 'significant impact' projects must add a vicinity map, contour lines, a vegetation and wetlands delineation, and a construction sequence. Plans must be stamped by a Massachusetts-registered professional engineer or certified erosion and sediment control professional and must meet the standards in the Massachusetts Stormwater Handbook and, for projects needing an NPDES construction permit, the accompanying stormwater pollution prevention plan.
The Department of Public Works has 90 calendar days to approve, conditionally approve, or disapprove a plan; missing that deadline lets the applicant proceed as filed. Permit holders must give the DPW two working days' notice before starting construction, clearing, rough grading, or final landscaping so inspections can be scheduled (notification is the only requirement on minor projects). If work violates the approved plan in a way that harms the environment, public health, or municipal facilities, the superintendent of public works or the director of municipal inspections can suspend the work entirely until the violation is corrected.
Violations & Fines
Working outside the approved erosion and sediment control plan, or without one where the site crosses the 2,500-square-foot/25%-of-lot or 100-cubic-yard thresholds, lets the superintendent of public works or director of municipal inspections halt all construction or site-alteration work until the violation is fixed. The ordinance does not set a separate dollar fine; enforcement runs through this stop-work power rather than a schedule of civil penalties.
Frequently Asked Questions
When does a Revere construction project need an erosion control plan?
Who reviews erosion control plans in Revere?
What happens if a builder violates Revere's erosion control plan?
Sources & Official References
Other rules in Revere
Compare Revere to another location·View the Massachusetts environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in this county handle erosion control.