Skip to main content
CityRuleLookup

Schaumburg, IL Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required
Land development permit before any earth movement
Stockpile cap
Topsoil stockpile volume ≤125% of on-site need
Stockpile slope
Temporary slopes capped at 2:1 (H:V)
Reseed trigger
Idle stockpiles over 2 weeks must be seeded
Standard referenced
NE Illinois erosion/sedimentation control manual + NPDES
Enforcement
Village engineer of community development

Summary

Schaumburg requires a land development permit before any clearing, grading or earth movement on a construction site. The permit application must include a soil erosion and sedimentation control plan, and the village engineer of community development inspects work and can halt it for noncompliance.

(H)Erosion, Sedimentation and Dust Control:(1)Issuance of a Land Development Permit: In the issuance of a land development permit, the following shall apply to any movement of earth and any sedimentation and erosion control plans:(a)Development shall be related to the topography and soils of the site so as to create the least potential for erosion... (d)Sediment basins, debris basins, desilting basins, silt traps, filters, silt fences or biofiltration wetlands should be installed and maintained to remove sediment from runoff waters from land undergoing treatment... (2)Engineering Requirements:(a)Before land is cleared, graded, transported or otherwise disturbed by the movement of earth for construction projects within the village, a land development permit embodying the proposed earth movement shall be obtained from the village engineer of community development.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56 Update 1 | Policy Manual: Supplement 20).

Full Breakdown

09(H), anyone clearing, grading, transporting or otherwise disturbing earth for a construction project in Schaumburg must first obtain a land development permit from the village engineer of community development. The application must include a grading plan with a soil erosion control plan covering all phases of construction and the period after completion, showing seeding mixtures and rates, sod type, seedbed prep, lime and fertilizer application, mulching, and who is legally responsible for maintaining erosion control structures once development is done. Topsoil stockpiles must be shown on the plan with a volume capped at no more than 125 percent of the topsoil actually needed on-site; off-site earthwork needs its own separate permit.

Temporary stockpile side slopes cannot exceed a 2:1 (horizontal to vertical) ratio, and any stockpile left in place more than two weeks must be seeded. Submissions must follow the 'Procedures and Standards for Soil Erosion and Sedimentation Control in Northeastern Illinois,' which the section expressly incorporates by reference, and must conform to NPDES standards as determined by the village engineer. Outlet control structures for stormwater and sediment must be installed before topsoil stripping begins, unless temporary outlet controls are approved. Dust on the project site must be controlled with a water wagon or similar device.

Natural vegetation near watercourses, wetlands and natural areas is to be left undisturbed wherever possible, and only the permitted area may be exposed, for the shortest practical time.

Violations & Fines

The village engineer of community development inspects graded sites and, if conditions do not match the approved plan, can order a stop to further work under § 151.09(J) until a revised grading plan is approved. Under § 151.09(K), the engineer may impose 'special precautions,' including additional drainage facilities, berms, terracing, compaction, cribbing, erosion plantings or a registered engineer's recommendations, if ongoing work threatens property, a public way, watercourse or drainage structure. The estimated cost of erosion control measures is folded into the subdivision security required under § 151.17(C), and that security can be used to complete corrective work if a developer fails to do it.

Frequently Asked Questions

Do I need a permit to grade or clear land in Schaumburg?
Yes. Section 151.09(H)(2)(a) requires a land development permit from the village engineer of community development before land is cleared, graded, transported or otherwise disturbed for a construction project, along with a soil erosion control plan.
How big can a topsoil stockpile be during construction?
The stockpile volume cannot exceed 125 percent of the topsoil that will actually be spread on the permitted site, per § 151.09(H)(2)(a)5. Side slopes are capped at 2:1, and stockpiles idle more than two weeks must be seeded.
Can Schaumburg stop construction over an erosion problem?
Yes. Under § 151.09(J), the village engineer of community development can halt further grading work if site conditions do not match the approved plan, and under § 151.09(K) can require special precautions like berms or terracing to prevent damage.
What standard governs Schaumburg's erosion control plans?
Plans must follow the 'Procedures and Standards for Soil Erosion and Sedimentation Control in Northeastern Illinois' and conform to NPDES standards, both incorporated by reference into § 151.09(H)(2)(c).

Sources & Official References

Other rules in Schaumburg

All Schaumburg rules

Compare Schaumburg to another location·View the Illinois environmental rules overview

Get notified when Erosion Control in Schaumburg, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Cook County handle erosion control.

Skokie, IL
Some Restrictions
Oak Lawn, IL
Some Restrictions
Chicago, IL
Some Restrictions
Evanston, IL
Some Restrictions
Tinley Park, IL
Some Restrictions
Arlington Heights, IL
Some Restrictions