Southampton, NY Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing standard
NYS Erosion Control Manual (Blue Book)
Inspection frequency
Every 7 days during active disturbance
Heightened frequency
Twice per 7 days above 5 disturbed acres
Inspector qualification
Licensed engineer or NYSDEC-endorsed CPESC
Enforcement tool
Stop-work order, Sec. 285-13B

Summary

Construction sites in the Town of Southampton must follow the New York State erosion and sediment control standards, and a qualified inspector has to walk the site at least once every seven days while soil disturbance is underway, twice every seven days once the site tops five disturbed acres.

The New York State Standards and Specifications for Erosion and Sediment Controls, hereafter referred to as the "Erosion Control Manual," in its most recent version (including applicable updates), also commonly known as the "Blue Book." ... For construction sites where soil disturbance activities ... are ongoing, the qualified inspector shall conduct a site inspection at least once every seven calendar days. ... For construction sites where soil disturbance activities are ongoing and the owner or operator has received authorization in accordance with the SPDES General Permit for Stormwater Discharges from Construction Activity to disturb greater than five acres of soil at any one time, the qualified inspector shall conduct at least two site inspections every seven calendar days.

Full Breakdown

Chapter 285 requires every stormwater pollution prevention plan to include an erosion and sediment control component designed to the current New York State Standards and Specifications for Erosion and Sediment Controls, known in the trade as the Blue Book, under Section 285-8A(2); a design that departs from that manual has to be shown equivalent to it. Section 285-9B(1) spells out what the erosion and sediment control piece of the plan must contain at minimum: a project description, a site map showing disturbed and undisturbed areas, soil types, a construction phasing plan, the specific erosion and sediment control practices for each phase with a schedule for how long each stays in place, and a temporary and permanent soil stabilization plan running through final stabilization.

Once construction starts, Section 285-10C requires a qualified inspector, a licensed engineer, a certified professional in erosion and sediment control, or another NYSDEC-endorsed professional, to inspect the site at least once every seven calendar days while soil disturbance is ongoing, and at least twice every seven days, separated by two full calendar days, once the project is authorized to disturb more than five acres at once. Sites can drop to a 30-day inspection cycle only after temporary stabilization is applied during a shutdown, such as a winter suspension, and inspections can stop altogether once final stabilization is certified. The Town's Stormwater Management Officer can halt construction outright if a project falls out of compliance with its approved erosion and sediment control plan.

Violations & Fines

Noncompliant erosion control work can draw a written notice of violation and a stop-work order under Section 285-13A and B, appealable within 15 days. Criminal penalties under Section 285-13D reach $1,000 and up to six months jail for a first offense, $1,000 to $2,500 for a second offense within five years, and $2,500 to $5,000 for a third offense, with each day a separate violation; the Town can also withhold a certificate of occupancy under Section 285-13H until the site is restored.

Frequently Asked Questions

What erosion control standard applies to construction in Southampton?
The current New York State Standards and Specifications for Erosion and Sediment Controls, the Blue Book, under Section 285-8A(2). Any design that deviates from it must be shown to perform equivalently.
How often must a Southampton construction site be inspected for erosion control?
At least once every seven calendar days while soil disturbance is ongoing under Section 285-10C(2)(a), rising to twice every seven days, at least two days apart, once the site is authorized to disturb more than five acres at once.
Who can inspect erosion controls on a Southampton job site?
A qualified inspector as defined in Section 285-5: a licensed professional engineer, a certified professional in erosion and sediment control, a registered landscape architect, or another NYSDEC-endorsed individual, or a trained person working directly under one of them.

Sources & Official References

Other rules in Southampton

All Southampton rules

New York rules heatmap·Compare Southampton to another location·View the New York environmental rules overview

Get notified when Erosion Control in Southampton, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Suffolk County handle erosion control.

Babylon, NY
Some Restrictions
Huntington, NY
Significant Restrictions
Islip, NY
Significant Restrictions