Southaven, MS Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- Southaven Code § 2-35, with §§ 2-33 and 2-34
- Plan required
- Land disturbance uncovering one (1) or more acres
- Stabilization deadline
- Within five (5) days of clearing or inactivity
- Phasing
- Required on sites disturbing more than twenty (20) acres
- Slope limit
- Cut and fill slopes no steeper than 2:1
- Inspection notice
- At least two (2) working days before each milestone
Summary
In the City of Southaven, no permit for land disturbing or construction activity that uncovers one (1) or more acres is granted without an AEA-approved erosion and sediment control plan. Soil must be stabilized within five (5) days of clearing or inactivity, and clearing waits until sediment control devices are installed and stabilized.
Phasing shall be required on all sites disturbing greater than twenty (20) acres, with the size of each phase to be established at plan review and as approved by the AEA. Clearing, except that necessary to establish sediment control devices, shall not begin until all sediment control devices have been installed and have been stabilized. Cut and fill slopes shall be no steeper than 2:1, except as approved by the AEA to meet other community or environmental objectives.(2)Erosion control. Soil must be stabilized within five (5) days of clearing or inactivity in construction. If vegetative erosion control methods, such as seeding, have not become established within two (2) weeks, the AEA may require that the site be revegetated, or that a non-vegetative option be employed. ... Soil stockpiles must be stabilized or covered at the end of each workday.
Full Breakdown
Chapter 4 of Title II of the Southaven Code regulates erosion and sediment control, and Section 2-35 holds the working standards. Section 2-33 states the purpose: to guide, regulate and control the design, construction, use and maintenance of any development or activity that disturbs the topsoil or moves earth in the City of Southaven.
Section 2-34 sets the permit gate. No person is granted a permit for land disturbing or construction activity that would require uncovering one (1) or more acres without approval of an erosion and sediment control plan by the AEA. Emergency activity immediately necessary to protect life, property or natural resources, and existing nursery and agricultural operations, need no permit.
Under § 2-35(1), clearing and grading of natural resources such as forests and wetlands is not permitted except in compliance with the rest of the title. Phasing is required on sites disturbing more than twenty (20) acres, and clearing cannot begin until sediment control devices are installed and stabilized, except the clearing needed to install them. Cut and fill slopes can be no steeper than 2:1 unless the AEA approves.
Under § 2-35(2), soil must be stabilized within five (5) days of clearing or inactivity. If seeding has not become established within two (2) weeks, the AEA can require revegetation or a non-vegetative option. Reseeding needs straw mulch or its equivalent until the cover crop is established over ninety (90) percent of the seeded area, and revegetated areas must show eighty-five (85) percent survival for one (1) year. Soil stockpiles must be stabilized or covered at the end of each workday, and a shutdown longer than two (2) weeks requires stabilizing the whole site.
Section 2-35(c) requires settling basins, sediment traps or tanks, and perimeter controls, and § 2-35(e) requires a temporary access road at every site. Under § 2-67(b), the permittee must notify the AEA at least two (2) working days before milestones such as the start of construction, completion of rough grading and final landscaping.
Violations & Fines
Section 2-83 requires a person receiving a notice of violation to halt all construction until the AEA confirms compliance. Under § 2-84 a violator can be required to restore land to its undisturbed condition, and the cost of city corrective action becomes a lien on the property. Section 2-85 holds occupation permits until corrections are accepted, and § 2-87 sets a fine up to $1,000.00 or imprisonment up to ninety (90) days, with each day a separate offense.
Frequently Asked Questions
When does Southaven require an erosion and sediment control plan?
How fast must bare soil be stabilized on a Southaven construction site?
What happens if grass seeding fails on a Southaven site?
Who inspects erosion controls and when must I call?
Sources & Official References
Other rules in Southaven
Compare Southaven to another location·View the Mississippi environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.