Springfield, OR Environmental Rules: Erosion Control (2026)
Key Facts
- Permit trigger
- 50 cu yd cut/fill, or 500 sq ft sensitive area, or 7,000 sq ft
- Wet weather season
- October 1 - April 30
- Permit types
- Type I (sensitive/commercial), Type II (1-2 unit residential)
- Plan preparer
- Licensed "Certified Professional" (Type I)
- Enforcing agency
- Development and Public Works Dept.
- Max forfeiture
- $500 first offense / $1,000 repeat
Summary
Construction sites in the City of Springfield, Oregon must control erosion and sediment under the Land and Drainage Alteration Program, SMC sections 8.400 to 8.436. A Land and Drainage Alteration Permit is required once work exceeds 50 cubic yards of cut or fill, disturbs 500 square feet in a sensitive area, or disturbs 7,000 square feet on a lot, with stricter wet-weather-season controls from October 1 through April 30.
8.400. General. Sections 8.400 to 8.436 establish regulations to: (1) Restrict the discharge of sediments and other construction related materials, including hazardous substances, into the public stormwater system in order to: ... Maintain the capacity of the public stormwater system by minimizing sedimentation; ... 8.412. ... Land and Drainage Alteration Permits. ... (1) Land and Drainage Alteration Permit Required. Unless otherwise provided in these regulations, no person shall commence any construction related activity without first obtaining from the city a Land and Drainage Alteration Permit, if the proposed construction related activity: (a) Exceeds 50 cubic yards or more of material on any one lot and/or adversely affects drainage from or onto adjoining properties; (b) Disturbs 500 square feet located in a sensitive area as specified in section 8.410; (c) Disturbs 7,000 square feet on any one lot or across contiguous lots under the same ownership; ... (e) Results in any amount of cut or fill for the placement of an inhabited structure.
Full Breakdown
SMC section 8.400 establishes the Land and Drainage Alteration Program to restrict sediment and hazardous-material discharges into the public stormwater system and to control excavating, grading, and earthwork. Section 8.404 applies it to land disturbance, structural development, new impervious surfaces, and dewatering, both inside city limits and in the urban transition area. Section 8.412 sets the permit triggers: more than 50 cubic yards of cut or fill, more than 500 square feet disturbed in a mapped sensitive area (steep slopes over 15 percent, drainage ways, wetlands, or floodplains per section 8.410), more than 7,000 square feet disturbed on a lot, disturbance of an acre or more, or any cut or fill for an inhabited structure.
Type I permits cover sensitive-area or commercial work and require a Land and Drainage Alteration Plan from a licensed 'Certified Professional' under section 8.406; Type II permits cover single-unit or duplex residential work outside sensitive areas. Smaller projects, like sheds under the disturbance thresholds or interior remodels, are waived from the permit itself but still must meet the outcome standards in section 8.408: keeping adjacent properties and the stormwater system free of sediment, covering exposed soil and stockpiles, and removing tracked material from the right-of-way by day's end.
During the wet weather season, October 1 through April 30, sites must additionally gravel entrances and protect stormwater facilities. The Development and Public Works Department administers permits and enforcement; violations of sections 8.400 to 8.436 are enforced as civil infractions under SMC sections 5.604 and 5.624.
Violations & Fines
Starting land-disturbing construction above the 50-cubic-yard, 500-square-foot-sensitive-area, or 7,000-square-foot thresholds without a Land and Drainage Alteration Permit, or letting sediment reach the public stormwater system or a neighboring property, violates SMC sections 8.404 and 8.408. The Land and Drainage Alteration Program is enforced as a civil infraction under SMC sections 5.604 and 5.624: up to $500 for a first violation in 365 days and up to $1,000 for a repeat, on top of any required cleanup.
Frequently Asked Questions
Do I need a permit to grade my lot in Springfield, Oregon?
What erosion control measures are required during construction?
What happens if a construction site lets mud wash into the street?
Who administers erosion control permits in Springfield?
Sources & Official References
Other rules in Springfield
Compare Springfield to another location·View the Oregon environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in this county handle erosion control.