Springfield, OR Environmental Rules: Stormwater Management (2026)
Key Facts
- Trigger: impervious surface
- 5,000 sq ft or more created/replaced
- Trigger: land disturbance
- 1 acre or more of development area
- Trigger: peak flow
- over 0.5 cubic feet per second
- Design storm depth
- first 1.4 inches of rainfall per event
- Treatment Standard removal rate
- 80% total suspended solids minimum
- Sanitary sewer discharge
- prohibited under SDC 4.3.110(C)(3)
- Design professional required
- Oregon licensed engineer
Summary
In the City of Springfield, Oregon, Development Code section 4.3.110 requires a site-specific stormwater management plan with structural controls for any development adding 5,000 square feet or more of impervious surface, disturbing an acre or more, or generating peak flows above 0.5 cubic feet per second. An Oregon-licensed engineer must design it.
4.3.110. Stormwater Management. ... (B) Applicability. ... The following development activities require the use of a site-specific stormwater management approach that incorporates 1 or more structural stormwater controls: (1) Development that creates or replaces 5,000 square feet or more of impervious surface area; (2) Development that disturbs 1 or more acres of land within the development area. ... (2) Technical Standards. ... (a) Site Performance Standard: The first 1.4 inches of rainfall from each storm event must be routed to 1 or more structural stormwater controls with sufficient capacity to fully infiltrate, evapotranspirate, and/or be reused on site without stormwater runoff discharging from the site; or (b) Treatment Standard: All rainfall not retained onsite, up to the first 1.4 inches of rainfall from each storm event, must be treated in compliance with the standards and design criteria in SDC 4.3.110(D). (3) Discharge to Sanitary Sewer Prohibited. The stormwater management system must be separated from, and not discharge to, any public or private sanitary sewer system.
Full Breakdown
Springfield Development Code 4.3.110 sets the City's stormwater management standard for triggered development within Development and Public Works jurisdiction. Section (B) applies the rule to any project that creates or replaces 5,000 square feet or more of impervious surface, disturbs one acre or more of the development area, or generates peak flows exceeding 0.5 cubic feet per second. Section (C)(1) requires the Stormwater Study and the structural control design to be prepared and stamped by an Oregon licensed engineer. Developers choose between two performance paths under (C)(2): the Site Performance Standard, routing the first 1.4 inches of rainfall from each storm to controls that fully infiltrate, evapotranspirate, or reuse it onsite with no discharge, or the alternative Treatment Standard, treating that same first 1.4 inches to remove at least 80 percent of total suspended solids under (D)(3)(b)(ii), reviewed through a Type 2 (or Type 3, where the underlying development already needs Type 3) process because the applicant must show the Site Performance Standard is technically infeasible due to shallow bedrock, high groundwater, soil instability, or similar site constraints.
Section (C)(3) bars any stormwater system from connecting to or discharging into a public or private sanitary sewer. Permeable pavement may offset impervious area but cannot itself treat runoff from other surfaces, and underground injection wells need Department of Environmental Quality approval. High-risk uses such as fuel dispensing facilities, bulk outdoor storage, and vehicle washing facilities face added source-control standards under Appendix H, and rooftop equipment needs secondary containment to keep leaks out of the stormwater system.
Violations & Fines
A development that skips the required stormwater study or structural controls, or that routes stormwater into the sanitary sewer in violation of SDC 4.3.110(C)(3), fails Development and Public Works review and cannot receive site plan or building permit approval. An Alternative Treatment Standard claim that cannot show technical infeasibility under (D)(2) is rejected, and unapproved underground injection wells operate without the required Department of Environmental Quality sign-off.
Frequently Asked Questions
What triggers a stormwater management plan for a Springfield development?
Can Springfield stormwater drain into the sanitary sewer?
How much rainfall must a Springfield stormwater system handle?
Who has to sign off on a Springfield stormwater design?
Sources & Official References
Other rules in Springfield
Compare Springfield to another location·View the Oregon environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities
How other cities in this county handle stormwater management.