Key Facts

Trigger threshold
5 or more residential dwelling units
Required capacity
40 percent of all parking spaces
Applies to
residential and mixed-use buildings
Governing section
Development Code Section 4.6.125(D)(3)
State cross-reference
electrical capacity defined in ORS 455.417

Summary

New residential and mixed-use buildings with 5 or more dwelling units in the City of Springfield, Oregon must wire for electric vehicle charging: Development Code Section 4.6.125(D)(3) requires enough electrical service capacity to accommodate 40 percent of all on-site vehicle parking spaces.

(D) Special Provisions. ... (3) Electric Vehicle Charging. Developments of new buildings with 5 or more residential dwelling units (includes both residential buildings and mixed-use buildings) that include on-site vehicle parking must provide electrical service capacity, as defined in ORS 455.417, to accommodate 40 percent of all vehicle parking spaces.

Full Breakdown

Springfield's parking chapter does not set a citywide minimum number of parking spaces, since Section 4.6.125(A) makes Table 4.6.2's figures merely suggested, but subsection (D)(3) carves out a mandatory electric vehicle standard that applies regardless: developments of new buildings with 5 or more residential dwelling units, including both residential buildings and mixed-use buildings, that include on-site vehicle parking must provide electrical service capacity, as defined in ORS 455.417, to accommodate 40 percent of all vehicle parking spaces. The requirement is about electrical capacity, not necessarily installed chargers at every space, so a developer must size the building's electrical service to support charging equipment at 4 in every 10 parking spaces even if only some spaces get a charger installed at construction.

The rule sits inside the same special-provisions subsection that also requires carpool and vanpool spaces for larger commercial and industrial developments and sets Campus Industrial District parking design standards, meaning EV capacity review happens alongside those other parking special provisions during site plan review. Because the standard reaches mixed-use buildings as well as purely residential ones, a 5-unit apartment building above ground-floor retail near downtown Main Street triggers the same 40 percent capacity requirement as a stand-alone apartment complex.

Violations & Fines

Failure to provide the required electric vehicle charging capacity is enforced the same way as any other Development Code parking standard: under Section 2.1.120, the Director can inspect a site whenever a violation is reasonably believed to have occurred, and Section 2.1.125 allows suspending or revoking a development approval issued for a project that does not meet the standard. A project cannot receive final building sign-off, since the Building Official verifies the approved plans, including the electrical capacity called for in Section 4.6.125(D)(3), before occupancy.

Frequently Asked Questions

Do new apartment buildings in Springfield, Oregon have to include EV charging?
Development Code Section 4.6.125(D)(3) requires new buildings with 5 or more residential dwelling units, including mixed-use buildings, to provide electrical service capacity for 40 percent of all on-site vehicle parking spaces if the development includes on-site parking at all.
Does the rule require an actual charger at every space?
No. The standard requires electrical service capacity, as defined in Oregon Revised Statutes 455.417, sufficient to accommodate 40 percent of parking spaces, meaning the building's electrical infrastructure must support that share of spaces even if chargers are not installed everywhere at construction.
Does a mixed-use building with ground-floor retail have to comply?
Yes. Section 4.6.125(D)(3) expressly covers both residential buildings and mixed-use buildings, so a mixed-use project with 5 or more dwelling units above commercial space must meet the same 40 percent electrical capacity requirement as a standalone apartment building.

Sources & Official References

Other rules in Springfield

All Springfield rules

Compare Springfield to another location·View the Oregon parking rules overview

Get notified when EV Charging in Springfield, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in this county handle ev charging.

Eugene, OR
Some Restrictions