Tallahassee, FL Environmental Rules: Erosion Control (2026)
Key Facts
- Governing law
- LDC § 5-88
- Stabilization deadline
- 14 days of inactivity
- Silt fence standard
- FDOT Type IV minimum
- Bench spacing on slopes
- Every 15 vertical feet
- Severe-grade barrier
- Double row Type IV silt fence + hogwire
- Enforcement tool
- Immediate stop-work order
Summary
Every environmental management permit application in Tallahassee must include a sediment and erosion control plan under Land Development Code Sec. 5-88. Sites cleared for more than 14 days without active work must be stabilized with vegetative ground cover, and failure to follow the plan brings an immediate stop-work order.
The sediment and erosion control plan is a document to be submitted as part of every environmental management permit application. It shall indicate the type and location of the best management practices to be implemented on the development site in order to minimize erosion and prevent sediment from leaving the site. Failure to properly execute the sediment and erosion control plan or any condition of the permit as it relates to sediment and erosion control shall result in immediate issuance of a "stop work" order that shall remain in effect until the site is stabilized and brought into compliance as determined by growth management staff.(8)Stabilization measures. Any site or portion thereof where work is not being performed, and which remains cleared for over 14 days, shall be stabilized through the establishment of appropriate vegetative ground cover.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Land Development Code: Supplement 75 | Code of Ordinances: Supplement 75).
Full Breakdown
Section 5-88 requires a sediment and erosion control plan as part of every environmental management permit application, detailing the best management practices a site will use to minimize erosion and keep sediment from leaving the property. The plan has to sequence construction so best management practices go in immediately, followed by the stormwater master facility or temporary sediment traps before the site is cleared in phases, and it must show how existing vegetation will be retained and denuded areas revegetated. Subsection (4) requires benches at least five feet wide on cut or fill slopes at intervals no greater than 15 vertical feet to control drainage and debris, and subsection (6) requires sediment basins or silt fences, with all silt fence meeting Florida Department of Transportation Type IV standards, placed below denuded areas and above sensitive water resources.
Subsection (8) sets a hard deadline: any site or portion of a site where work has stopped and that has stayed cleared for more than 14 days must be stabilized with appropriate vegetative ground cover, and all disturbed areas must be permanently stabilized once development activity finishes. Properties with severe grades (over 20 percent slope) need a heavy-duty silt barrier under subsection (8) item 8: a double row of Type IV silt fence, one row at the toe of the slope and a second row ten feet beyond it, backed by hogwire fencing on six-foot wooden posts set eight feet on center.
Violations & Fines
Failing to properly execute the sediment and erosion control plan, or any permit condition tied to it, results in immediate issuance of a stop-work order under Sec. 5-88 that stays in effect until growth management staff confirms the site is stabilized and back in compliance. Sediment that accumulates in the stormwater system from construction activity must be removed immediately, and the environmental inspector can require additional best management practices beyond what the approved plan specifies at any point during construction.
Frequently Asked Questions
How long can a construction site in Tallahassee sit cleared without erosion control?
What happens if a Tallahassee builder doesn't follow the erosion control plan?
Are there extra erosion control requirements for steep sites in Tallahassee?
Sources & Official References
Other rules in Tallahassee
Florida rules heatmap·Compare Tallahassee to another location·View the Florida environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.