Vacaville, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
grading over 50 cu yd or affecting foundations
Erosion control deadline
installed by October 1 each year
Slope trigger
cut/fill over 3 ft of erodible material
Hillside cap
grading barred on slopes 25%+ without approval
Enforcement tools
stop-work order, permit suspension/revocation

Summary

Vacaville regulates erosion and sediment control through Chapter 14.19's Grading, Erosion, and Sediment Control Ordinance. Under Section 14.19.244.010(D), the Building Official, City Engineer, or Director of Public Works can require erosion control on any graded slope, and disturbed slopes over three feet of erodible material must have approved erosion control installed by October 1st ahead of the rainy season.

D. Erosion Control Measures. All grading shall be subject to erosion control measures as required by the Building Official, the City Engineer, or the Director of Public Works, as appropriate. Erosion control measure shall include the following: 1. Filter Materials. Filter materials shall be provided to prevent any debris and dirt from the construction activity from flowing into the City storm drain system; 2. Disturbed Areas. The faces of cut and fill slopes which accept overland or sheet flow or any cut or fill slope of erodible material over three feet in height shall have approved erosion control installed immediately following rough or finished grading between October 1st and April 30th. Slopes graded between April 30th and October 1st shall have erosion control installed no later than October 1st.

Full Breakdown

010; the Building Official issues permits for residential or nonresidential grading moving 5,000 cubic yards or less, while the City Engineer issues permits for larger volumes, subdivision grading, or cuts and fills exceeding five vertical feet. Small projects are exempt only if they stay under 50 cubic yards, avoid hillside areas, and involve no special land forms, though any disturbance of an acre or more still triggers state construction stormwater permit coverage regardless of volume. 010(D) requires filter materials to keep construction debris and dirt out of the City storm drain system, and any cut or fill slope over three feet of erodible material that accepts overland flow must have approved erosion control installed immediately after grading if the work finishes between October 1st and April 30th, or no later than October 1st if graded during the dry season; the City Engineer, Building Official, or Director of Public Works may require a cash deposit to guarantee that deadline is met.

Additional devices such as check dams, sedimentation basins, riprap, or hydroseeding must be used when necessary to control erosion and protect water quality. Hillside grading on slopes of 25 percent or greater is prohibited unless specifically approved by the Director of Community Development and the City Engineer, and contractors must also control windblown dust and debris under subsection F. 020(A)(7) before final approval.

Violations & Fines

Grading without a permit, or failing to install erosion control by the October 1st deadline, is enforced under Sections 14.19.242.060 through .090, which let the City issue a notice of noncompliance, suspend or revoke the grading permit, and issue a stop-work order until remedial erosion control is installed. Enforcement of Division 14.19 also runs through the administrative fine and nuisance-abatement procedures in Sections 14.26.050.010 through .210, exposing a responsible party to infraction fines and abatement costs.

Frequently Asked Questions

When must erosion control be installed on a Vacaville grading site?
Vacaville Municipal Code Section 14.19.244.010(D)(2) requires approved erosion control on qualifying cut and fill slopes immediately after grading finishes between October 1 and April 30, or no later than October 1 if the slope was graded during the dry season between April 30 and October 1.
Do I need a grading permit for a small backyard project?
Not always. Section 14.19.242.010(C) exempts isolated grading under 50 cubic yards outside hillside areas and special land forms, along with minor shallow excavations, but any disturbance of an acre or more still needs state construction stormwater permit coverage.
Can Vacaville require a cash deposit for erosion control?
Yes. Section 14.19.244.010(D)(2) lets the Building Official, City Engineer, or Director of Public Works require that money be deposited to guarantee erosion control measures are installed by the October 1 deadline.

Sources & Official References

Other rules in Vacaville

All Vacaville rules

California rules heatmap·Compare Vacaville to another location·View the California environmental rules overview

Get notified when Erosion Control in Vacaville, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Solano County handle erosion control.

Vallejo, CA
Some Restrictions
Fairfield, CA
Some Restrictions