Warwick, RI Environmental Rules: Erosion Control (2026)
Key Facts
- Permitting agency
- Building Official
- Permit trigger
- Any land-disturbing development project
- Exempt additions
- Under 1,000 sq ft, 100+ ft from water
- Fine
- Up to $250/day per violation
- Bond required
- Near watercourses or on 10%+ slopes
Summary
Warwick requires anyone disturbing vegetation, grades, or land contours for a development project to get a permit from the building official before work starts. Chapter 68 exempts small home additions and minor excavations, and violators face fines up to $250 per day plus revocation of plan approval.
This chapter shall apply to all development and re-development occurring within the city. No person shall engage in development projects without receiving approval from the building official, unless specifically exempted by section 68-4 of this chapter. ... It shall be unlawful for any person to disturb any existing vegetation, grades, and contours of land without first applying for and receiving a permit from the building official.
Full Breakdown
Under Section 68-3, the erosion and sediment control chapter applies to every development and re-development project in Warwick, and Section 68-4 makes it unlawful to disturb existing vegetation, grades, or contours without first applying for and receiving a building official permit. Exemptions in Section 68-4 cover additions to single- or two-family homes under 1,000 square feet that sit more than 100 feet from a watercourse on slopes under ten percent, minor excavations under four feet deep that move less than 50 cubic yards of material, and landscaping grading capped at 1,000 square feet and 18 cubic yards of fill.
To get a permit, an applicant files an erosion and sediment control plan under Section 68-5 for review by the building official, public works director, and planning director, who must act within ten days of receiving that input; failure to respond within 21 days counts as no objection. Where land disturbance sits within 100 feet of a watercourse, inside a flood hazard district, or on slopes over ten percent, Section 68-10 requires the applicant to post a performance bond sized to cover the cost of the approved erosion controls. L. 1956, § 45-23-14 for a subdivision.
Violations & Fines
Violating any provision of Chapter 68 carries a fine of up to $250.00 per day for each day the violation continues, under Section 68-16. The building official can also revoke or suspend plan approval and halt work under Section 68-17, require temporary fixes within five days and permanent correction within 30 days, and place a lien on the property for the city's cost of completing corrective work if the owner does not act.
Frequently Asked Questions
Do I need a permit to grade my yard in Warwick?
What Warwick construction projects are exempt from the erosion control permit?
What happens if I skip the Warwick erosion control permit?
Sources & Official References
Other rules in Warwick
Compare Warwick to another location·View the Rhode Island environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.