Warwick, RI Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Regulated zones
A, AE, AH, AO, A99, V, VE
AO zone minimum elevation
2 ft above highest adjacent grade
Permit required for
any construction/development in flood zone
Enforcing office
Building official
Accessory structure exemption cap
structure value under $1,000
BFE data trigger
subdivisions over 50 lots or 5 acres

Summary

Warwick requires a building or development permit for any construction in a mapped special flood hazard area under City Code § 8-5, administered by the building official. In AO flood zones without a FEMA depth number, new or substantially improved structures must be elevated or flood-proofed at least two feet above the highest adjacent grade, and floodway encroachments that raise base flood levels are barred entirely.

Building permit. All proposed construction or other development within a special flood hazard area shall require a permit... Within zones AO on the FIRM, new and substantially improved residential structures shall have the top of the lowest floor at least as high as the FIRM's depth number above the highest adjacent grade and non-residential structures shall be elevated or flood-proofed above the highest adjacent grade to at least as high as the depth number on the FIRM. On FIRMs without a depth number for the AO zone, structures shall be elevated or floodproofed to at least two feet above the highest adjacent grade. ... Enforcement. The building official shall enforce all provisions as applicable in reference to G.L. § 23-27.3-108.1. Penalties. Every person who shall violate any provision of this Code shall be subject to penalties put forth in G.L. § 23-27.3-122.3.

Full Breakdown

Section 8-5 establishes the city's floodplain overlay district covering all zones A, AE, AH, AO, A99, V, and VE mapped on the Kent County Flood Insurance Rate Map administered by FEMA, using panels dated as recently as October 2, 2015. Any proposed construction or other development inside a special flood hazard area, not just building work but filling, grading, excavation, mining, drilling, or storage of materials, requires a permit before work starts, and applicants must first show that every other required federal or state approval, including from the Rhode Island Coastal Resources Management Council or the Department of Environmental Management, has been obtained.

In AO zones, the code sets a concrete elevation floor: a residential structure's lowest floor must sit at least as high as the FIRM's depth number above the highest adjacent grade, and where the FIRM lists no depth number, the minimum is two feet above the highest adjacent grade; non-residential structures must be elevated or flood-proofed to the same standard. In A1-30 and AE zones along a designated regulatory floodway, no encroachment is allowed if it would raise base flood levels during the base flood discharge.

Base flood elevation data is required for subdivisions or other developments larger than 50 lots or five acres, whichever is smaller, within unnumbered A zones. Detached accessory structures under $1,000 in value, such as sheds or garages, can skip the elevation requirement only if they are unfinished, outside the floodway, not used to store hazardous materials, wet flood-proofed, and anchored against flotation. 3.

Violations & Fines

Building or developing inside a mapped special flood hazard area without the required permit, or without meeting the AO zone's two-foot minimum elevation above the highest adjacent grade, is presumed to be a violation until the owner produces the missing lowest-floor elevation documentation, flood-proofing certificate, or floodway encroachment calculations. The building official enforces the chapter under G.L. § 23-27.3-108.1, and the penalties for a violation are those set out in G.L. § 23-27.3-122.3, the state building code's enforcement statute.

Frequently Asked Questions

Do I need a permit to build in a Warwick flood zone?
Yes. Section 8-5 requires a permit for any construction or other development, not just buildings, inside a mapped special flood hazard area, including filling, grading, excavation, or storage of materials. The application must show that every other required federal or state permit, such as from the Rhode Island Coastal Resources Management Council, has already been secured before the city will issue its own permit.
How high above grade must a house be built in an AO flood zone?
If the FIRM does not list a depth number for the AO zone, § 8-5 sets the floor at two feet above the highest adjacent grade for new or substantially improved residential structures, and non-residential buildings must be elevated or flood-proofed to that same two-foot minimum. Where a depth number is shown, the structure must instead meet that depth number above grade.
Are sheds exempt from Warwick's flood elevation rules?
A detached accessory structure such as a shed or garage can skip the elevation requirement only if it is valued under $1,000, has an unfinished interior not used for habitation, sits outside the floodway, is not used to store hazardous materials, is wet flood-proofed to allow floodwater to pass through automatically, and is firmly anchored against flotation or collapse.

Sources & Official References

Other rules in Warwick

All Warwick rules

Compare Warwick to another location·View the Rhode Island environmental rules overview

Get notified when Flood Elevation Requirements in Warwick, RI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.