Key Facts

Freeboard added to BFE
2 feet
No-BFE zones minimum elevation
2 feet above highest adjacent grade
Governs
Reference level height of new/improved structures
Certification required
FEMA elevation certificate, Form 086-0-33
Administered by
Floodplain administrator (zoning administrator)

Summary

Sec. 32-315 defines the "regulatory flood protection elevation" that governs construction in Granville County's mapped flood hazard areas as the base flood elevation (BFE) plus two feet of freeboard. Where FEMA has not mapped a BFE, the same elevation floor applies at two feet above the highest adjacent grade.

These county ordinances apply to unincorporated areas of Granville County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Freeboard means the height added to the base flood elevation (BFE) to account for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of urbanization on the watershed. The base flood elevation plus the freeboard establishes the "regulatory flood protection elevation." ... Regulatory flood protection elevation means the "base flood elevation" plus the "freeboard". In "special flood hazard areas" where base flood elevations (BFEs) have been determined, this elevation shall be the BFE plus two feet of freeboard. In "special flood hazard areas" where no BFE has been established, this elevation shall be at least two feet above the highest adjacent grade.

Full Breakdown

The code defines "freeboard" as "the height added to the base flood elevation (BFE) to account for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions," and it sets that add-on at two feet for Granville County. Sec. 32-315 then defines "regulatory flood protection elevation" (RFPE) as the BFE plus that two-foot freeboard in any special flood hazard area where FEMA has published a BFE, or at least two feet above the highest adjacent grade where no BFE has been established.

That elevation is the number Sec. 32-330 uses to set the reference level, including any basement, for both new residential construction and substantial improvements, and for non-residential buildings that are elevated rather than floodproofed. Electrical, heating, plumbing and air-conditioning equipment must sit at or above the RFPE too, so it cannot flood even when the structure around it meets the elevation standard. A registered land surveyor or professional engineer must certify the reference-level elevation on a FEMA elevation certificate (Form 086-0-33), submitted before construction starts, again within seven days of setting the reference level, and a final time as as-built documentation before the county issues a certificate of occupancy. The floodplain administrator, who is the county's zoning administrator, reviews each certificate and can require corrections before construction proceeds.

Violations & Fines

Sec. 32-323 makes failing to build to the regulatory flood protection elevation, or failing to submit a required elevation certificate, a class 1 misdemeanor under G.S. 143-215.58, punishable by a fine of not more than $100.00 or 30 days imprisonment, or both, with each day of noncompliance a separate offense. The floodplain administrator can also withhold a certificate of occupancy until a corrected elevation certificate is submitted.

Frequently Asked Questions

How much freeboard does Granville County require above the base flood elevation?
Sec. 32-315 sets the freeboard at two feet. The county's "regulatory flood protection elevation" is defined as the base flood elevation plus that two feet, and new construction and substantial improvements in a special flood hazard area must have their reference level, including any basement, elevated no lower than that combined number.
What elevation applies if FEMA has not mapped a base flood elevation for my property?
Sec. 32-315 still requires an elevation floor: the regulatory flood protection elevation is at least two feet above the highest adjacent grade when no BFE has been established. Sec. 32-331 adds that new construction on an unmapped approximate zone A parcel must still be elevated to that same floor.
Who has to certify that my home meets the required flood elevation?
A registered land surveyor or professional engineer must certify the reference-level elevation on a FEMA elevation certificate, submitted to the floodplain administrator before construction starts, again within seven days of setting the reference level, and once more as as-built documentation before a certificate of occupancy is issued.

Sources & Official References

Other rules in Granville County

All Granville County rules

Compare Granville County to another location·View the North Carolina environmental rules overview

Get notified when Flood Elevation Requirements in Granville County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.