Key Facts

AO zone standard
FIRM depth number, or 2 ft minimum
A zone / other zones
At or above base flood elevation
Who certifies
Registered engineer or surveyor
Administrator
City engineer (floodplain administrator)
Violation
Misdemeanor, § 14-238

Summary

Hemet requires new and substantially improved buildings in mapped flood hazard areas to elevate the lowest floor to or above the base flood elevation, verified by a registered engineer or surveyor.

Residential construction, new or substantial improvement, shall have the lowest floor, including basement: a.In an AO zone, elevated above the highest adjacent grade to a height equal to or exceeding the depth number specified in feet on the FIRM, or elevated at least two feet above the highest adjacent grade if no depth number is specified. b.In an A zone, elevated to or above the base flood elevation, as determined by this community. c.In all other zones, elevated to or above the base flood elevation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 69 Update 2).

Full Breakdown

In the city's special flood hazard areas, Hemet City Code § 14-276(c)(1) sets the elevation standard for new residential construction: in an AO zone, the lowest floor must clear the highest adjacent grade by the FIRM-specified depth number (or two feet if none is specified); in an A zone and all other zones, the lowest floor must sit at or above the base flood elevation. A registered engineer or surveyor must certify the finished elevation to the floodplain administrator (the city engineer) before the building is occupied.

Violations & Fines

Building without required elevation or certification is a misdemeanor under § 14-238; the city council may also take direct legal action to stop or remedy the violation.

Frequently Asked Questions

How high must a new house be built in a Hemet flood zone?
At or above the base flood elevation in most zones; in an AO zone, above the adjacent grade by the depth shown on the FIRM or at least 2 feet if none is shown.
Who verifies the elevation is correct?
A registered professional engineer or surveyor must certify the lowest floor elevation to the city's floodplain administrator before the certificate of occupancy is granted.

Sources & Official References

Other rules in Hemet

All Hemet rules

California rules heatmap·Compare Hemet to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Hemet, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Riverside County handle flood elevation requirements.

Menifee, CA
Some Restrictions
Murrieta, CA
Some Restrictions
Temecula, CA
Some Restrictions
Riverside, CA
Some Restrictions
Palm Springs, CA
Some Restrictions
Corona, CA
Significant Restrictions
Moreno Valley, CA
Significant Restrictions