Skip to main content
CityRuleLookup

Menifee, CA Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Minimum freeboard, AE/AH/A1-30
2 feet above BFE
AO zone standard
2 feet above depth number, or 4 feet
Certification required from
Registered civil engineer or surveyor
Applies to
New construction and substantial improvements
Nonresidential alternative
Flood proofing to same elevation

Summary

New or substantially improved residential structures in Menifee's special flood hazard areas must have their lowest floor, including any basement, elevated at least 2 feet above the base flood elevation shown on FEMA's Flood Insurance Rate Map, certified by a civil engineer or surveyor.

BASE FLOOD ELEVATION (BFE). The elevation shown on the Flood Insurance Rate Map for Zones AE, AH, A1-30, VE and V1-V30 that indicates the water surface elevation resulting from a flood that has a 1% or greater chance of being equaled or exceeded in any given year... (a) Residential construction. All new construction or substantial improvements of residential structures shall have the lowest floor, including basement: a. In AE, AH, A1-30 Zones, elevated at least 2 feet above the base flood elevation. b. In an AO zone, elevated above the highest adjacent grade to a height two feet above the depth number specified in feet on the FIRM, or elevated at least four feet above the highest adjacent grade if no depth number is specified. c. In an A zone, without BFE's specified on the FIRM [unnumbered A zone], elevated at least two feet above the base flood elevation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-15: Supplement contains: Local legislation current through Ordinance 2026-432, passed 4-15-2026).

Full Breakdown

020 as the water surface elevation shown on the Flood Insurance Rate Map for Zones AE, AH, A1-30, VE and V1-V30 resulting from a flood with a 1% or greater annual chance of being equaled or exceeded. 050(A)(3)(a) sets the elevation standard, or freeboard, that new construction and substantial improvements must clear: in Zones AE, AH and A1-30 the lowest floor, including any basement, must sit at least 2 feet above the BFE; in an AO zone it must be elevated above the highest adjacent grade to a height 2 feet above the depth number shown on the FIRM, or at least 4 feet above the highest adjacent grade if no depth number is given; and in an unnumbered A zone with no BFE specified on the FIRM, the lowest floor must still be at least 2 feet above the base flood elevation.

Once the structure is finished, the elevation of the lowest floor must be certified by a registered civil engineer or licensed land surveyor and verified by the city's building inspector, with that certification filed with the Floodplain Administrator. 050(A)(3)(b), certified by a registered civil engineer or architect as watertight and capable of resisting hydrostatic and hydrodynamic loads. 050(A)(3)(e).

Violations & Fines

Building below the required freeboard, or without the required post-construction elevation certification, places the structure out of compliance with Chapter 4.2 and is a misdemeanor under Section 4.2.030(C), enforceable by the Floodplain Administrator (the City Engineer) through administrative citation or other lawful action. Where base flood elevation data has not already been supplied, Section 4.2.040(B)(3) directs the Floodplain Administrator to obtain and apply the best available federal or state elevation data before approving a permit, so a project cannot skip the standard for lack of a mapped BFE.

Frequently Asked Questions

How high above the base flood elevation must a Menifee home be built?
Section 4.2.050(A)(3)(a) requires the lowest floor, including any basement, to sit at least 2 feet above the base flood elevation in AE, AH and A1-30 zones, with adjusted standards for AO and unnumbered A zones.
Who verifies the elevation was built correctly?
A registered civil engineer or licensed land surveyor must certify the completed lowest-floor elevation, and the city's building inspector verifies it, with the certification filed with the Floodplain Administrator per Section 4.2.050(A)(3)(a)2.
Can a nonresidential building skip the elevation requirement?
Yes, under Section 4.2.050(A)(3)(b) it can be flood proofed instead, watertight with walls substantially impermeable to water and structurally able to resist flood loads, certified by a registered civil engineer or architect.

Sources & Official References

Other rules in Menifee

All Menifee rules

California rules heatmap·Compare Menifee to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Menifee, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Riverside County handle flood elevation requirements.

Murrieta, CA
Some Restrictions
Temecula, CA
Some Restrictions
Riverside, CA
Some Restrictions
Palm Springs, CA
Some Restrictions
Corona, CA
Significant Restrictions
Moreno Valley, CA
Significant Restrictions