Corona, CA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Governing section
- § 18.20.010(C), elevation and floodproofing
- BFE defined at
- § 18.08.022
- Residential standard
- Lowest floor to or above BFE
- AH/AO/VO alternative
- Highest adjacent grade + depth, min 2 ft
- Certification required from
- Engineer, surveyor, or Building Inspector
- Enclosure vents
- 1 sq in per sq ft, below 1 ft
Summary
Corona requires new and substantially improved residential structures in a mapped flood hazard area to have their lowest floor, including any basement, built to or above the base flood elevation (BFE) shown on the FIRM. A licensed engineer, surveyor, or the Building Inspector must certify the finished elevation before occupancy.
New construction and substantial improvement of any residential structure shall have the lowest floor, including basement, elevated to or above the BFE. Upon the completion of the structure, the elevation of the lowest floor, including basement, shall be certified by a registered professional engineer or surveyor or verified by the Building Inspector to be properly elevated. The certification or verification shall be provided to the Floodplain Administrator.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-56: Supplement contains: Local legislation passed through Ord. 3423, passed 12-3-2025).
Full Breakdown
022 defines BFE as the base flood elevation shown on the Flood Insurance Rate Map for Zones AE, AH, A1-30, VE and V1-V30, representing the water surface elevation of a flood with a 1% or greater annual chance of occurrence. 010(C)(1) sets the elevation standard: new construction and substantial improvement of any residential structure must have the lowest floor, including basement, elevated to or above the BFE, with the finished elevation certified to the Floodplain Administrator by a registered engineer or surveyor, or verified by the Building Inspector.
010(C)(2) instead requires the lowest floor elevated above the highest adjacent grade by the depth number printed on the FIRM, or at least two feet if none is shown. 010(C)(3), be dry floodproofed watertight below the base flood level, with structural components able to resist hydrostatic and hydrodynamic loads, certified by a registered engineer or architect. 010(C)(4), have at least two openings totaling one square inch of net area per square foot of enclosed area, with opening bottoms no higher than one foot above grade, so floodwaters can enter and exit automatically.
The code does not add a freeboard margin above the mapped BFE for the standard residential case; the requirement is the FIRM elevation itself, or the AH/AO/VO alternative described above.
Violations & Fines
Failing to elevate or floodproof a structure as required in an area of special flood hazard is a misdemeanor under Corona Code of Ordinances § 18.12.030, punishable as provided in § 1.08.025, since Title 18's compliance and penalty provisions apply to the whole floodplain management title, including the Chapter 18.20 construction standards. The City Council may also take other lawful action to remedy an unpermitted or non-conforming structure.
Frequently Asked Questions
How high must I build above the base flood elevation in Corona?
What counts as the base flood elevation in Corona?
What if my lot is in Zone AH, AO or VO with no BFE listed?
Can a nonresidential building in Corona skip elevating to the BFE?
Sources & Official References
Other rules in Corona
California rules heatmap·Compare Corona to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Riverside County handle flood elevation requirements.