Key Facts

Delineated watercourse
Best available elevation plus one foot of freeboard
Zone AO, no depth number
Three feet above the highest adjacent grade
Class IV critical facilities
Additional two feet of freeboard
Lowest floor
At or above LDFE, confirmed by an Elevation Certificate
Undelineated watercourse trigger
Contributory drainage area of 50 acres or more
Fine
Not more than $1250 per violation

Summary

In the City of Perth Amboy, New Jersey, the Local Design Flood Elevation for a delineated watercourse is the Best Available Flood Hazard Data Area elevation plus one foot of freeboard, or as N.J.A.C. 7:13 describes. Zone AO areas add the printed depth number plus one foot, and Class IV critical facilities add two feet.

The Local Design Flood Elevation (LDFE) is established in the flood hazard areas determined in Section 231-102.2, above, using the best available flood hazard data sources, and the Flood Hazard Area Control Act minimum Statewide elevation requirements for lowest floors in A, Coastal A, and V zones, ASCE 24 requirements for critical facilities as specified by the building code, plus additional freeboard as specified by this chapter. At a minimum, the Local Design Flood Elevation shall be as follows: (1) For a delineated watercourse, the elevation associated with the Best Available Flood Hazard Data Area determined in Section 231-102.2, above plus one foot or as described by N.J.A.C. 7:13 of freeboard; or ... (3) AO Zones - For Zone AO areas on the municipality's FIRM (or on preliminary flood elevation guidance from FEMA), the Local Design Flood Elevation is determined from the FIRM panel as the highest adjacent grade plus the depth number specified plus one foot of freeboard. If no depth number is specified, the Local Design Flood Elevation is three feet above the highest adjacent grade.

Full Breakdown

Section 231-102.3 of the Perth Amboy City Code sets the Local Design Flood Elevation (LDFE) that governs how high buildings in the City of Perth Amboy, Middlesex County, New Jersey must be built above flooding. The elevation is set using the best available flood hazard data, the Flood Hazard Area Control Act minimum Statewide elevation requirements for lowest floors in A, Coastal A, and V zones, and ASCE 24 requirements for critical facilities, plus the freeboard the chapter specifies. Under the definitions, no project's LDFE can be lower than a permit-specified Flood Hazard Area Design Flood Elevation or a valid NJDEP Flood Hazard Area Verification Letter plus the freeboard required in ASCE 24 and the effective FEMA Base Flood Elevation.

For a delineated watercourse the elevation is that of the Best Available Flood Hazard Data Area plus one foot of freeboard, or the freeboard N.J.A.C. 7:13 describes. Where a watercourse is undelineated and has a contributory drainage area of 50 acres or more, the applicant must supply either an unexpired NJDEP Flood Hazard Area Verification plus one foot of freeboard and any additional freeboard required by ASCE 24, or a determination using Method 5 or Method 6 from N.J.A.C. 7:13 plus one foot of freeboard, sealed and submitted under Section 231-105.2-3. In Zone AO areas the LDFE is the highest adjacent grade plus the depth number specified plus one foot of freeboard; with no depth number it is three feet above the highest adjacent grade.

Critical facilities carry more. New and substantially improved Flood Design Class IV Critical Facilities must meet the higher of the 0.2% annual chance (500-year) flood elevation or the Flood Hazard Area Design Flood Elevation with an additional two feet of freeboard. Class III Critical Facilities in coastal high hazard areas use the same higher-of test with an additional one foot.

The LDFE then drives construction. Under § 231-801.2(A)(3), new construction and substantial improvement of any habitable building in flood hazard areas needs the lowest floor, including basement, and the attendant utilities elevated to or above the LDFE, in conformance with ASCE 24 Chapter 7 and confirmed by an Elevation Certificate. Non-residential structures either meet the same elevation or are designed so that the structure below the LDFE is floodproofed, with a Floodproofing Certificate. Where design flood elevations are not specified, § 231-103.7 authorizes the Floodplain Administrator to require the applicant to use Federal, State or other data, or a sealed engineering determination.

Violations & Fines

Failing to comply with Chapter 231, including its elevation standards, is a violation under N.J.S.A. 40:49-5, and § 231-101.8 sets a fine of not more than $1250. Each day is a separate violation, but the owner is afforded a thirty-day period to cure or abate and a hearing before the court. After that period a greater fine can be imposed if abatement is not substantially completed, and a repeat conviction within one year adds a repeat-offender fine.

Frequently Asked Questions

How much freeboard does Perth Amboy require?
For a delineated watercourse the Local Design Flood Elevation is the Best Available Flood Hazard Data Area elevation plus one foot of freeboard, or as described by N.J.A.C. 7:13. Zone AO areas add one foot to the depth number, Class IV critical facilities add two feet, and Class III facilities in coastal high hazard areas add one foot.
What is the elevation rule in a Zone AO area in the City of Perth Amboy?
The LDFE is determined from the FIRM panel as the highest adjacent grade plus the depth number specified plus one foot of freeboard. If no depth number is specified, the Local Design Flood Elevation is three feet above the highest adjacent grade. The same rule applies to Zone AO areas on preliminary FEMA flood elevation guidance.
Does my new house in a Perth Amboy flood zone need an Elevation Certificate?
Yes. Under § 231-801.2(A)(3), new construction and substantial improvement of any habitable building in flood hazard areas must have the lowest floor, including basement, and attendant utilities elevated to or above the LDFE, conform to ASCE 24 Chapter 7, and be confirmed by an Elevation Certificate.
What if no flood elevation is mapped for my lot?
For an undelineated watercourse with a contributory drainage area of 50 acres or more, you must provide an unexpired NJDEP Flood Hazard Area Verification plus one foot of freeboard, or a Method 5 or Method 6 determination plus one foot, sealed by the design professional. Section 231-103.7 also lets the Floodplain Administrator require federal, state or engineering data.

Sources & Official References

Other rules in Perth Amboy

All Perth Amboy rules

Compare Perth Amboy to another location·View the New Jersey environmental rules overview

Get notified when Flood Elevation Requirements in Perth Amboy, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in this county handle flood elevation requirements.

Edison, NJ
Some Restrictions