Key Facts

Freeboard required
Two feet above regional flood elevation
Applies to
New construction, manufactured homes, substantial improvements
Fill extent
At least 15 feet beyond structure limits
Basement exception
Must be engineered watertight, no lower floor
Penalty
Up to $50 per day plus costs, § 7.6.9

Summary

Portage County requires two feet of freeboard above the regional flood elevation before a structure counts as protected, and any new residential construction or substantial improvement in the floodfringe must have its lowest floor built up to that flood protection elevation.

These county ordinances apply to unincorporated areas of Portage County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Flood protection elevation means an elevation of two feet of freeboard above the water surface profile elevation designated for the regional flood. ... 1.All new construction, including placement of manufactured homes, and substantial improvement of residential structures, shall have the lowest floor elevated to or above the flood protection elevation on fill. The fill around the structure shall be one foot or more above the regional flood elevation extending at least 15 feet beyond the limits of the structure.

Full Breakdown

Portage County Code § 7.1.6(10) defines 'flood protection elevation' as an elevation of two feet of freeboard above the water surface profile elevation designated for the regional flood, the extra margin the county builds in above the base flood level to absorb wave action, debris, and mapping uncertainty. That defined elevation becomes an operative construction standard in the Floodfringe District under § 7.6.4(3)(a)1: any new construction, including placement of a manufactured home, and any substantial improvement of a residential structure in the floodfringe must have its lowest floor elevated to or above the flood protection elevation on fill, and the fill itself must extend at least one foot or more above the regional flood elevation for a minimum of 15 feet beyond the structure's limits.

Section 7.6.4(3)(a)2 allows one narrow alternative to full fill: a basement or crawlspace floor can sit at the regional flood elevation itself, without the two-foot freeboard, only if it is engineered watertight, with walls substantially impermeable to water and structural components capable of resisting hydrostatic and hydrodynamic loads and buoyancy, and the code adds flatly that 'no floor of any kind is allowed below the regional flood elevation.' Contiguous dryland access from the structure to land outside the floodplain is required under § 7.6.4(3)(a)3, unless the county grants a documented exception for a road below the regional flood elevation under § 7.6.4(3)(a)4, which itself requires written assurance from police, fire, and emergency services that they can still reach the structure by wheeled vehicle during a regional flood.

Violations & Fines

As with every other floodplain standard, failing to build to the flood protection elevation required by § 7.6.4(3)(a) is enforced under § 7.6.9: the County Corporation Counsel prosecutes, a conviction forfeits not more than $50.00 to Portage County plus taxable costs, each day the low floor remains noncompliant is a separate offense, and the violation can be abated as a public nuisance under Wis. Stats. § 87.30.

Frequently Asked Questions

What is Portage County's freeboard requirement?
Section 7.1.6(10) defines the county's 'flood protection elevation' as two feet of freeboard above the regional flood elevation, and § 7.6.4(3)(a)1 requires new construction and substantial improvements of residential structures in the floodfringe to have their lowest floor built up to or above that elevation on fill.
Can I have a basement below the flood protection elevation?
Only if it meets § 7.6.4(3)(a)2's engineering test: the basement or crawlspace floor may sit at the regional flood elevation, without the two-foot freeboard, if designed watertight with impermeable walls and structural components able to resist hydrostatic and hydrodynamic loads, and no floor may go below the regional flood elevation at all.
How far must the fill extend around an elevated house?
Section 7.6.4(3)(a)1 requires fill placed to reach the flood protection elevation to extend at least one foot or more above the regional flood elevation and reach at least 15 feet beyond the limits of the structure in every direction.

Sources & Official References

Other rules in Portage County

All Portage County rules

Compare Portage County to another location·View the Wisconsin environmental rules overview

Get notified when Flood Elevation Requirements in Portage County, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.