Key Facts

Residential lowest floor
At least two feet higher than base flood elevation
Nonresidential lowest floor
At least one foot higher, or floodproofed to one foot higher
Fill extent
At least 15 feet beyond the building limits
Chemical storage
At least one foot above the base flood elevation
Substantial improvement
Cost equals or exceeds 50% of market value
As-built proof
Elevation certificate from licensed surveyor or engineer

Summary

In the Town of Union outside the Villages of Endicott and Johnson City, new residential buildings in the flood-fringe must have the lowest floor, basement included, at least two feet above base flood elevation. Nonresidential buildings need one foot above, or floodproofing to one foot above. Fill must extend 15 feet past the building.

(2) Buildings, provided that: (a) The elevation of the lowest floor, including basement, of all new residential construction or substantial improvements to existing residential buildings within the flood-fringe area shall be at least two feet higher than the base flood elevation. (b) The elevation of the lowest floor, including basement, of all new nonresidential buildings or substantial improvements to existing nonresidential buildings within the flood-fringe area shall be at least one foot higher than the base flood elevation or, together with attendant utility and sanitary facilities, shall be floodproofed up to one foot higher than the base flood elevation. ... (d) Fill deposited for the purpose of elevating the lowest floor above the base flood elevation shall extend at least 15 feet beyond the limits of any building erected thereon. Such fill shall be protected against erosion by riprap, vegetation, bulkheading or other forms of cover. (e) Any storage facility for chemicals, explosives or flammable liquids shall be located at an elevation at least one foot higher than the elevation of the base flood.

Full Breakdown

Section 121-10.4 governs the flood-fringe, defined in subsection A as the part of the area of special flood hazard inside the one-hundred-year-flood (base flood) boundary and outside the regulatory floodway. Every use there other than the low-damage uses in § 121-10.1 is allowed only as a special permit use from the Planning Board, and the building standards below are conditions of that permit.

For residential buildings, § 121-10.4(B)(2)(a) sets the freeboard: the lowest floor, including basement, of all new residential construction, or substantial improvements to existing residential buildings, must be at least two feet higher than the base flood elevation. The definition of substantial improvement in § 121-4 reaches any repair, reconstruction or improvement costing 50% or more of the structure's market value, excluding land value.

For nonresidential buildings, subsection (b) requires the lowest floor, including basement, to be at least one foot higher than the base flood elevation, or the building and its attendant utility and sanitary facilities must be floodproofed up to one foot higher than the base flood elevation. Subsection (c) requires all uses in the flood-fringe to be floodproofed in the manner outlined in §§ 121-13 and 121-14.

Fill used to raise the lowest floor must extend at least 15 feet beyond the limits of any building built on it and must be protected against erosion by riprap, vegetation, bulkheading or other cover (subsection (d)). Any storage facility for chemicals, explosives or flammable liquids must sit at an elevation at least one foot higher than the base flood (subsection (e)).

Proving the number takes paperwork. Where the Planning Board deems it necessary in unnumbered A Zones, § 121-10.5 has the applicant establish the base flood elevation from federal or state data, such as the Army Corps of Engineers, the Soil Conservation Service or the New York State Department of Environmental Conservation, or from a certified determination by a New York State professional engineer and land surveyor. Under § 121-11 the application states the proposed lowest floor elevation in relation to mean sea level, and the permit holder files an as-built elevation certificate prepared by a licensed land surveyor or professional engineer. Further work before the certificate is approved is at the permit holder's risk.

Violations & Fines

A building built below the required elevation violates Chapter 121, and § 121-8 sets a fine of no more than $250, imprisonment of not more than 15 days, or both, with each day of noncompliance a separate offense. Section 121-11 treats deficiencies in the elevation certificate as cause for a stop-work order unless corrected immediately, and a structure without an approved variance is reported to FEMA.

Frequently Asked Questions

How high must a new house sit above base flood elevation in the Town of Union flood-fringe?
Section 121-10.4(B)(2)(a) requires the lowest floor, including basement, of all new residential construction to be at least two feet higher than the base flood elevation. The same two-foot rule applies to substantial improvements of existing residential buildings in the flood-fringe.
What elevation applies to a commercial building in the flood-fringe?
The lowest floor, including basement, must be at least one foot higher than the base flood elevation. The alternative in § 121-10.4(B)(2)(b) is to floodproof the building, together with its attendant utility and sanitary facilities, up to one foot higher than the base flood elevation, in the manner outlined in §§ 121-13 and 121-14.
How much fill can be used to raise a building site?
The code sets no cap in the fill provision. It requires fill deposited to elevate the lowest floor above base flood elevation to extend at least 15 feet beyond the limits of any building on it, and to be protected against erosion by riprap, vegetation, bulkheading or other cover.
How does the Town verify the floor elevation after construction?
Under § 121-11 the permit holder submits a certificate of the as-built elevation of the lowest floor in relation to mean sea level, prepared by or under a licensed land surveyor or professional engineer. Work done before the certificate is approved is at the permit holder's risk, and deficiencies bring a stop-work order.

Sources & Official References

Other rules in Union

All Union rules

New York rules heatmap·Compare Union to another location·View the New York environmental rules overview

Get notified when Flood Elevation Requirements in Union, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.