Key Facts

Governing section
City Code § 425-71B(3)
Standard freeboard
1 foot above mapped elevation
Class IV critical facility freeboard
2 feet (ASCE 24)
Class III coastal facility freeboard
1 foot
AO Zone default elevation
3 feet above grade
Verifying official
Construction Official/Floodplain Administrator

Summary

New and substantially improved buildings in Vineland's flood hazard areas must meet a local design flood elevation that adds required freeboard above the base flood elevation, set under City Code Section 425-71B(3). Ordinary construction along a delineated watercourse needs at least one foot of freeboard, while new Class IV critical facilities need two feet of freeboard above the 500-year flood elevation, per ASCE 24.

§ 425-71. Flood damage prevention. ... (3) Establishing the local design flood elevation (LDFE). The local design flood elevation (LDFE) is established in the flood hazard areas determined in Subsection B(2), above, using the best available flood hazard data sources, and the Flood Hazard Area Control Act minimum statewide elevation requirements for lowest floors in A, Coastal A, and V Zones, ASCE 24 requirements for critical facilities as specified by the building code, plus additional freeboard as specified by this section. At a minimum, the local design flood elevation shall be as follows: (a) For a delineated watercourse, the elevation associated with the best available flood hazard data area determined in Subsection B(2), above plus one foot or as described by N.J.A.C. 7:13 of freeboard; or ... (d) Class IV critical facilities. For any proposed development of new and substantially improved flood design Class IV critical facilities, the local design flood elevation must be the higher of the 0.2% annual chance (500-year) flood elevation or the flood hazard area design flood elevation with an additional two feet of freeboard in accordance with ASCE 24.

Full Breakdown

City Code Section 425-71B(3) sets Vineland's local design flood elevation, the minimum elevation to which new construction and substantial improvements in a flood hazard area must be built, always above the base flood elevation shown on the effective Flood Insurance Rate Maps. For a building along a delineated watercourse, the local design flood elevation is the mapped flood hazard elevation plus one foot of freeboard, or the freeboard the state Flood Hazard Area Control Act requires if greater. Where no map or study covers a watercourse with 50 or more acres of drainage area, an applicant must submit either an unexpired state flood hazard area verification plus one foot of freeboard, or an engineering determination under state Method 5 or Method 6 plus one foot of freeboard and any additional freeboard ASCE 24 requires, sealed by a licensed professional engineer.

In AO Zones, the local design flood elevation is the highest adjacent grade plus the FIRM-specified depth number plus one foot of freeboard, or three feet above the highest adjacent grade if no depth number is listed. Development of a new or substantially improved Class IV critical facility, such as a hospital, police or fire station, or emergency operations center, must reach the higher of the 0.2%-annual-chance flood elevation or the flood hazard area design flood elevation, plus two feet of freeboard under ASCE 24.

A Class III critical facility in a coastal high-hazard area needs the same 500-year comparison with one additional foot of freeboard. The Construction Official, as Floodplain Administrator, verifies that every development permit's stated elevation correctly applies these standards before construction begins.

Violations & Fines

Section 425-71 makes failure to build to the required local design flood elevation a code violation like any other noncompliance with the floodplain regulations, punishable by a fine of up to $1,250, up to 90 days' imprisonment or community service, with each day of continuing noncompliance a separate offense and a 30-day cure period before a higher fine can be imposed. The Floodplain Administrator can also refuse or condition permit approval until the elevation, engineering data and freeboard requirements are satisfied.

Frequently Asked Questions

How much freeboard does Vineland require above the base flood elevation?
Under Section 425-71B(3), ordinary new construction and substantial improvements along a delineated watercourse must reach the mapped flood hazard elevation plus one foot of freeboard, or more if the state Flood Hazard Area Control Act requires it. Class IV critical facilities need two feet of ASCE 24 freeboard above the higher of the 500-year flood elevation or the flood hazard area design elevation.
What elevation applies in a Vineland AO Zone with no listed flood depth?
Section 425-71B(3) sets the local design flood elevation at three feet above the highest adjacent grade when a FIRM panel lists Zone AO but no depth number. Where a depth number is specified, the elevation is the highest adjacent grade plus that depth plus one foot of freeboard.
Who checks whether a Vineland building permit meets the flood elevation rules?
The Construction Official, designated Floodplain Administrator under Section 425-71, reviews every permit application in a flood hazard area to confirm the applicant's stated local design flood elevation correctly applies the best available FEMA and state data, including any required freeboard for critical facilities.

Sources & Official References

Other rules in Vineland

All Vineland rules

Compare Vineland to another location·View the New Jersey environmental rules overview

Get notified when Flood Elevation Requirements in Vineland, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.