Vineland, NJ Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing section
- City Code § 425-72
- Major development trigger
- 1+ acre disturbed since 2/2/2004
- Impervious surface trigger
- 5,000+ sq ft since 2/2/2004
- Motor vehicle surface trigger
- 5,000+ sq ft since 3/2/2021
- TSS removal standard
- 80% of anticipated annual load
- Water quality design storm
- 1.25 inches in two hours
- CO withheld until
- as-built BMP certification filed
Summary
City Code Section 425-72 sets Vineland's stormwater management standards for "major development," covering any project that disturbs one acre or more, or adds 5,000 square feet or more of impervious or motor vehicle surface, since specified 2004 and 2021 trigger dates. Regulated projects must control erosion, promote groundwater recharge, limit runoff quantity, and remove at least 80 percent of total suspended solids from the required design storm.
§ 425-72. Stormwater control. ... (2) Purpose. The purpose of this section is to establish minimum stormwater management requirements and controls for "major development," as defined below in Subsection B. ... MAJOR DEVELOPMENT (1) Any development that meets the definition of "major subdivision" in § 425-64A or the definition of "major site plan" in § 425-66A. "Major development" also means an individual "development," as well as multiple developments that individually or collectively result in: (a) The disturbance of one or more acres of land since February 2, 2004; (b) The creation of 5,000 square feet or more of regulated impervious surface since February 2, 2004; ... (b) Stormwater management measures shall be designed to reduce the postconstruction load of total suspended solids (TSS) in stormwater runoff generated from the water quality design storm as follows: [1] Eighty percent TSS removal of the anticipated load, expressed as an annual average shall be achieved for the stormwater runoff from the net increase of motor vehicle surface. ... The water quality design storm is 1.25 inches of rainfall in two hours.
Full Breakdown
Vineland's stormwater control ordinance, City Code Section 425-72, implements the state Stormwater Management Rules and applies to "major development": any project meeting the city's own major subdivision or major site plan thresholds, or any development, alone or combined with other phases of a common plan, that disturbs one acre or more of land since February 2, 2004, creates 5,000 square feet or more of regulated impervious surface since February 2, 2004, or creates 5,000 square feet or more of regulated motor vehicle surface since March 2, 2021.
Regulated projects must incorporate green infrastructure and low-impact development practices to control erosion, promote groundwater recharge, manage runoff quantity, and treat runoff quality. Erosion control must meet the state Soil Erosion and Sediment Control Act standards. Where a project increases regulated motor vehicle surface by 5,000 square feet or more, its stormwater measures must remove at least 80 percent of the anticipated annual average total suspended solids load from the net increase in that surface, calculated against a water quality design storm of 1.25 inches of rainfall over two hours.
Projects already subject to a numeric pollutant discharge limit for suspended solids are exempt from the local standard. Applications submitted before July 17, 2024, remain subject to the requirements in effect on July 16, 2024. Where this section conflicts with another city ordinance, rule or law, the more restrictive standard controls, and the section does not relieve an applicant of separately required state or federal permits.
Violations & Fines
Section 425-72 enforces compliance mainly through the certificate of occupancy process: the City withholds CO clearance until the design engineer certifies in writing that any stormwater management BMP was built to the approved design, was properly cleaned after 90 percent of construction was complete, and operates as intended, and until as-built permeability test results and an as-built survey are on file with the City.
Frequently Asked Questions
What triggers Vineland's stormwater management requirements under Section 425-72?
How much stormwater pollution must a Vineland development remove?
Can Vineland withhold a certificate of occupancy over stormwater noncompliance?
Sources & Official References
Other rules in Vineland
Compare Vineland to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.