Rutherford County, TN Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Residential freeboard (AE Zone)
3 ft above BFE
Non-residential freeboard (AE Zone)
1 ft above BFE
Approximate A Zone standard
3 ft above highest adjacent grade
Minimum pad elevation
1 ft above BFE
Enclosure vent sizing
1 sq in per sq ft enclosed
Governing section
Zoning Ordinance § 1005 B

Summary

In unincorporated Rutherford County, new homes and substantially improved residences in AE flood zones must have their lowest floor built at least 3 feet above the Base Flood Elevation, a foot higher than FEMA's baseline standard.

City-specific rules exist: Murfreesboro has its own flood elevation requirements rules that differ from Rutherford County's county-level regulations. If you live in Murfreesboro, check the city-specific page instead.

In AE Zones where Base Flood Elevation data is available, new construction and substantial improvement of any residential building (or manufactured home) shall have the lowest floor, including basement, elevated to no lower than three (3) feet above the Base Flood Elevation. Minimum pad elevations shall be a minimum of one (1) foot above the established BFE or a minimum of one (1) foot above the highest known water level in areas subject to periodic flooding or inundation.

Full Breakdown

Rutherford County's Zoning Ordinance imposes a 3-foot freeboard requirement that exceeds the federal minimum. 1, in AE Zones where Base Flood Elevation (BFE) data is available, new construction and substantial improvement of any residential building or manufactured home must have the lowest floor, including any basement, elevated to no lower than three feet above the BFE. Minimum pad elevations must be at least one foot above the established BFE, or one foot above the highest known water level in areas subject to periodic flooding. Where BFE data has not been established (approximate A Zones) and no alternative data is available, the Floodplain Administrator requires the lowest floor to sit at least three feet above the highest adjacent grade, as defined in Section 1002.

2: only one foot above the BFE where data is available, or three feet above the highest adjacent grade in approximate A Zones, and non-residential buildings may flood-proof in lieu of elevating if a Tennessee-registered professional engineer or architect certifies the design meets accepted standards and files that certification with the Administrator under Subsection 1004 B. 3 requires flood vent openings sized at one square inch of net area per square foot of enclosed area, with the bottom of every opening no higher than one foot above finished grade, so hydrostatic forces equalize automatically during a flood event.

5. Any structure spanning multiple flood zones or multiple BFEs must meet the standard for the most hazardous zone and the highest BFE, per the general provisions in Subsection 1005 A.

Violations & Fines

The Floodplain Administrator in the Planning & Engineering department reviews elevation certificates before a certificate of occupancy issues; a lowest floor built below the required 3-foot freeboard, or enclosure vents that fail the one-square-inch-per-square-foot standard, is a permit and inspection failure that blocks occupancy until corrected or documented with a registered engineer's flood-proofing certification.

Frequently Asked Questions

How high above base flood elevation must a new house be built in unincorporated Rutherford County?
At least 3 feet above the Base Flood Elevation for the lowest floor, including any basement, when the home sits in an AE Zone with established BFE data, per Zoning Ordinance Section 1005 B.1. This freeboard exceeds FEMA's baseline requirement of matching the BFE exactly.
What if my lot is in an A Zone with no published Base Flood Elevation?
The Floodplain Administrator requires the lowest floor elevated at least 3 feet above the highest adjacent grade, as defined in Section 1002, when no BFE or alternative data exists for that approximate A Zone under Section 1005 B.1.
Can a commercial building be flood-proofed instead of elevated?
Yes. Section 1005 B.2 allows non-residential buildings in A Zones to be flood-proofed rather than elevated if all areas below the required elevation are watertight and a Tennessee-registered engineer or architect certifies the design to the Administrator under Subsection 1004 B.
Are enclosed areas below the elevated floor allowed?
Yes, but Section 1005 B.3 requires them designed to auto-equalize hydrostatic forces: at least two openings totaling one square inch of net area per square foot of enclosed space, with opening bottoms no higher than one foot above finished grade, and no finished living space permitted inside.

Sources & Official References

Other rules in Rutherford County

All Rutherford County rules

Compare Rutherford County to another location·View the Tennessee environmental rules overview

Get notified when Flood Elevation Requirements in Rutherford County, TN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.