Key Facts
- Minimum fill height
- 12 inches above 100-year flood
- Buffer required
- 10 feet around each structure
- Floodway subdivisions
- prohibited outright
- Determined by
- City Engineer
- Governing code
- Waterloo City Code § 11-5-4
Summary
In the City of Waterloo, Iowa, the subdivision code requires any new plat in a flood-prone area to raise the lowest water entry level of every structure at least twelve inches above the 100-year flood elevation, with a ten-foot buffer maintained around the building, and the City Council can flatly refuse to approve subdivision of land the city has designated as floodway.
5. Areas Of Poor Drainage: Whenever a plat is submitted for an area which is subject to flooding, the city council may approve such subdivision provided that the applicant fills the affected area of said subdivision to an elevation sufficient to place the "lowest water entry level" as herein defined, of any structure at a minimum of twelve inches (12") above the elevation of the 100-year flood, for an area at least ten feet (10') equidistant around the structure, as determined by the city engineer. ... ... 7. Floodway Areas: The city council shall prohibit the subdivision of land for residential, commercial or industrial development located within areas of the city which are designated as floodway.
Full Breakdown
Waterloo City Code § 11-5-4, the drainage and storm sewers chapter of the subdivision regulations (Title 11), governs how flood-prone land can be platted inside the city limits. Under subsection B.5, "Areas Of Poor Drainage," the City Council may approve a subdivision plat covering land subject to flooding only if the applicant raises the site so that the "lowest water entry level" of every structure sits at least twelve inches above the 100-year flood elevation, extending that fill at least ten feet in every direction around the building.
The City Engineer determines the exact elevation and the boundaries of the required fill area, and the plat must also lay out an overflow zone along any stream or watercourse bank wide enough to carry high water; no fill, structure, or obstruction may be placed inside that overflow zone. Subsection B.6 lets the Council go further and bar subdivision entirely within a "flood fringe area" when it finds the restriction necessary for health, safety, water conservation, drainage or sanitary facilities. Subsection B.7 draws the hardest line: the Council must prohibit subdivision of any land inside the city designated floodway, whether the proposed use is residential, commercial, or industrial.
This provision sits entirely inside the platting process administered by the Planning, Programming and Zoning Commission and the City Engineer; it is separate from Waterloo's standalone zoning ordinance, which is not part of this code.
Violations & Fines
There is no separate fine for this section; the consequence is that the Planning, Programming and Zoning Commission will not recommend, and the City Council will not approve, a final subdivision plat that fails to meet the twelve-inch fill requirement, lacks a defined overflow zone, or proposes lots inside a designated floodway. The Council may withhold approval of any plat outright until the developer corrects the flooding or drainage deficiency the City Engineer identifies.
Frequently Asked Questions
Does this rule apply to a house I already own?
What is the 'lowest water entry level'?
Can the City ever allow building in a floodway?
Who decides where the buffer and overflow zone go?
Sources & Official References
Other rules in Waterloo
Compare Waterloo to another location·View the Iowa environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.