Brick, NJ Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in Brick, NJ, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Permit required
- Development permit before any construction or fill
- Administered by
- Municipal Engineer
- Penalty
- Up to $500/day, 180 days jail
- Basis
- FEMA maps, Community No. 345285
Summary
Brick Township requires a development permit before any construction, fill, or land alteration in FEMA-mapped special flood hazard areas, with elevation and floodproofing certification and Municipal Engineer review of every application.
A development permit shall be obtained before construction or development begins, including placement of manufactured homes, within any area of special flood hazard established in § 196-7. Application for a development permit shall be made on forms furnished by the Municipal Engineer and may include, but not be limited to; plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in question; existing or proposed structures, fill, storage of materials, drainage facilities; and the location of the foregoing. Specifically, the following information is required:
A. A plot plan specifying the flood zone involved (with base flood elevation), showing elevation(s) in the NAVD 1988 Datum of the lowest floor, including basement, garage and crawl space of all structures, or the lowest structural member, if applicable. [Amended 10-26-2021 by Ord. No. 21-21]
B. The elevation, in relation to mean sea level, to which any nonresidential structure has been floodproofed.
C. Plans showing how any nonresidential floodproofed structure will meet the floodproofing criteria of § 196-18B and, after the structure is built, a certification by a registered professional engineer or architect that the structure, as built, meets the criteria of § 196-18B.
D. A description of the extent to which any watercourse will be altered or relocated as a result of proposed development.
E.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4577344; v53 updated 2025-12-09; through 12-09-2025).
Full Breakdown
Chapter 196 of the Brick Township Code applies to all areas of special flood hazard within the township, based on FEMA flood insurance maps for Community No. 345285. Anyone building, filling, or altering land in those zones must first get a development permit from the Municipal Engineer, submitting a plot plan showing the flood zone, base flood elevation, and the elevation of the lowest floor. Nonresidential floodproofed structures need a registered engineer's or architect's certification that they meet the code's floodproofing criteria. Building without the permit is a misdemeanor.
Violations & Fines
Building, filling, or altering land in a special flood hazard area without a development permit is a misdemeanor: up to $500 per day, up to 180 days imprisonment, or both, with each day a separate violation.
Frequently Asked Questions
Do I need a permit to build in a Brick Township flood zone?
What happens if I build in a flood hazard area without a permit?
Sources & Official References
Other rules in Brick
Compare Brick to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Zones in Nearby Cities
How other cities in this county handle flood zones.