FEMA flood zone rules in Camarillo, CA, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.

Key Facts

Permit required
Flood area development permit, Sec. 16.34.300
Elevation standard
1.0 ft above base flood elevation
Floodway rule
No encroachment without no-rise engineer certification
Administering agency
Director of Engineering Services
Appeal deadline
10 days to city clerk, fee required
Variance minimum lot
One-half acre or less

Summary

Camarillo requires a flood area development permit before any construction begins in a FEMA special flood hazard area. New and substantially improved structures must be elevated at least 1 foot above base flood elevation, and the Director of Engineering Services administers and enforces the standard.

New construction and substantial improvement of any structure shall have the bottom of the floor slab, lowest floor beam or basement floor elevated to a minimum of 1.0 foot above the base flood elevation. Nonresidential structures will meet the standards in subsection C3 of this section. Upon completion of the structure the elevation of the lowest floor, including the basement, shall be certified by a registered professional engineer or surveyor or verified by the local building inspector that the elevation requirements have been met.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27 Update 1).

Full Breakdown

300. The application must show the proposed elevation of the lowest habitable floor relative to the National Geodetic Vertical Datum of 1929, and in Zone AO must show existing grade and proposed floor elevation. 310, reviews every application to confirm the site is reasonably safe from flooding and that the project will not raise the base flood water surface elevation more than one foot. 0 foot above base flood elevation, certified on completion by a registered professional engineer, surveyor, or the local building inspector. 400(C)(3), certified by a registered engineer or architect.

450 bars encroachments, including fill and new construction, into a designated floodway unless an engineer certifies no increase in flood levels during the base flood discharge; where no floodway is mapped, the code imposes a setback equal to five times the stream's top-of-bank width or twenty feet on each side, whichever is greater. 520, limited to lots of one-half acre or less bordered by existing below-grade structures, and require a written notice that flood insurance premiums can run as high as $25 per $100 of coverage on the resulting structure.

Violations & Fines

Failing to submit the required elevation certification under Section 16.34.320(C)(2) is cause for the city to issue a stop-work order on the project. Under the Section 16.34.130 definition of 'violation,' any structure lacking an elevation certificate or other required compliance documentation is presumed to be in violation until that documentation is produced. Appeals of a director decision go to the Planning Commission, filed with the city clerk within 10 days with a council-set administrative fee; commission decisions may be further appealed to the city council within 10 days.

Frequently Asked Questions

Do I need a permit to build in a Camarillo flood zone?
Yes. Section 16.34.300 requires a flood area development permit before any construction or development begins within a FEMA-designated area of special flood hazard, reviewed by the Director of Engineering Services against the standards in Chapter 16.34.
How high above flood level must a new house be built?
Section 16.34.400(C)(1) sets the floor of new construction and substantial improvements at a minimum of 1.0 foot above the base flood elevation, verified on completion by a registered engineer, surveyor, or the city building inspector.
Can I build inside a mapped floodway in Camarillo?
Only if a registered professional engineer certifies the project will not increase flood levels during the base flood discharge; Section 16.34.450 otherwise prohibits fill, new construction and other encroachments into designated floodways.
What happens if I skip the elevation certificate?
The city can issue a stop-work order under Section 16.34.320(C)(2), and under the Section 16.34.130 definitions the structure is presumed in violation until the missing elevation or compliance documentation is filed with the Director.

Sources & Official References

Other rules in Camarillo

All Camarillo rules

California rules heatmap·Compare Camarillo to another location·View the California environmental rules overview

Get notified when Flood Zones in Camarillo, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Zones in Nearby Cities

How other cities in Ventura County handle flood zones.

Moorpark, CA
Some Restrictions
Simi Valley, CA
Some Restrictions
Ventura, CA
Significant Restrictions
Oxnard, CA
Significant Restrictions
Thousand Oaks, CA
Significant Restrictions