Camarillo, CA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Minimum freeboard
- 1.0 foot above base flood elevation
- Governing chapter
- Municipal Code Chapter 16.34, Flood Damage Protection
- Enforcing official
- Director of engineering services
- Non-compliance consequence
- Stop-work order for missing certification
- Variance body
- Planning commission, appealable to city council
- Insurance warning
- Premiums may rise up to $25 per $100 coverage
Summary
New construction and substantial improvements in Camarillo's mapped flood hazard areas must have their lowest floor at least one foot above the base flood elevation. The city's director of engineering services enforces the standard under Municipal Code Chapter 16.34, and skipping the required elevation certification triggers an automatic stop-work order on the project.
C.Elevation and Floodproofing.1.New construction and substantial improvement of any structure shall have the bottom of the floor slab, lowest floor beam or basement floor elevated to a minimum of 1.0 foot above the base flood elevation. Nonresidential structures will meet the standards in subsection C3 of this section. Upon completion of the structure the elevation of the lowest floor, including the basement, shall be certified by a registered professional engineer or surveyor or verified by the local building inspector that the elevation requirements have been met. Notification of compliance shall be recorded as set forth in Section 16.34.320C.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27 Update 1).
Full Breakdown
Camarillo's flood damage prevention chapter, Municipal Code Chapter 16.34, applies to every area of special flood hazard shown on the city's Flood Insurance Rate Map. Under Section 16.34.400(C), new construction and substantial improvement of any structure must have the bottom of the floor slab, the lowest floor beam, or the basement floor elevated to a minimum of 1.0 foot above the base flood elevation, the freeboard the city adds on top of FEMA's mapped level. Structures in Zone AO must instead sit above the flood depth number printed on the FIRM, or two feet above the highest adjacent grade if no depth number is shown. Nonresidential buildings may floodproof instead of elevate, but a registered engineer or architect must certify the floodproofing can withstand the flood depths, pressures, and hydrostatic and hydrodynamic loads expected at the site.
The director of engineering services administers the chapter, reviewing every development permit application for compliance. Once a structure is complete, its lowest-floor elevation must be certified by a registered professional engineer or surveyor, or verified by the city's building inspector, and recorded under Section 16.34.320(C). Skipping this step is grounds for the director to issue a stop-work order. Owners on a lot of one-half acre or less surrounded by existing structures built below the base flood level may seek a variance from the planning commission under Sections 16.34.520 and 16.34.530, but the commission cannot grant one inside a mapped floodway if it would raise flood levels. A denied applicant can appeal to the planning commission within ten days, then to the city council. Any variance granted comes with a mandatory written notice warning that building below the base flood elevation can raise flood insurance premiums by as much as twenty-five dollars per one hundred dollars of coverage.
Violations & Fines
Building without the required 1.0-foot freeboard, or without submitting the lowest-floor elevation certification, lets the director of engineering services issue a stop-work order under Section 16.34.320(C) and withhold approval until the deficiency is corrected. Encroaching into a mapped floodway without an engineer's no-rise certification is prohibited outright under Section 16.34.450(A). Owners who build below the base flood elevation under a variance still face higher flood-insurance premiums, up to twenty-five dollars per one hundred dollars of coverage, under Section 16.34.540.
Frequently Asked Questions
How far above base flood elevation must new construction sit in Camarillo?
Can a nonresidential building floodproof instead of elevate?
What happens if I skip the elevation certification?
Can I get a variance to build below the base flood elevation?
Sources & Official References
Other rules in Camarillo
California rules heatmap·Compare Camarillo to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Ventura County handle flood elevation requirements.