FEMA flood zone rules in Peoria, IL, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.

Key Facts

Governing section
City Code Sec. 12-5
Permit authority
Director of public works
Floodway BFE cap
1.0 foot cumulative increase max
Minimum fine
Not less than $50.00 per violation
Enforcement escalation
10-day notice, then circuit court injunction

Summary

Any development in Peoria's Special Flood Hazard Area needs a development permit from the director of public works before work starts. City Code Ch. 12 sets the permit standard, site-plan requirements, and a minimum $50 fine per day for skipping it, running under the National Flood Insurance Program.

No person not exempted by state law shall commence any development in the SFHA without first obtaining a development permit from the director of public works. The director of public works shall not issue a development permit if the proposed development does not meet the requirements of this chapter. ... Failure to obtain a permit for development in the SFHA or failure to comply with the requirements of a permit or conditions of a variance resolution shall be deemed to be a violation of this chapter. ... Any person who violates this chapter shall upon conviction thereof be fined not less than $50.00 nor more than as provided in section 1-5 of this Code.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 119).

Full Breakdown

Chapter 12, Flood Damage Prevention and Control, was enacted under the city's police powers under the Illinois Municipal Code to keep Peoria eligible for the National Flood Insurance Program. Sec. 12-5 requires anyone not exempted by state law to obtain a development permit from the director of public works before commencing any development in the Special Flood Hazard Area (SFHA), and the director cannot issue that permit unless the proposal meets the chapter's requirements. The application must include scaled site drawings showing property lines, existing and proposed grade elevations, building locations and dimensions, and the lowest floor elevation of any proposed building.

The director compares the site elevation to the base flood elevation; land shown to have sat above base flood elevation before the site's first flood insurance rate map identification is treated as outside the SFHA. The director must also tell applicants about any other required local, state, or federal permits and cannot issue the city permit until those are obtained. Sec. 0-foot cumulative increase in base flood elevation for the affected stream reach. Sec. 12-3 assigns the director of public works ongoing duties: verifying that development meets the chapter, maintaining elevation and floodproofing records, inspecting projects for compliance, and coordinating with state and federal floodplain agencies.

Violations & Fines

Sec. 12-11 makes failure to obtain a development permit, or noncompliance with a permit's or variance's conditions, a violation. The corporation counsel investigates and gives the owner written notice; if the owner fails to correct the violation within ten days, the city can seek a circuit court injunction to force compliance, and a court conviction carries a fine of not less than $50.00, escalating up to the general penalty cap in Sec. 1-5, with each day of continuing violation treated as a separate offense. The corporation counsel can also warn the owner that a willful violation may be treated as increasing flood damages, which can suspend coverage under a standard flood insurance policy.

Frequently Asked Questions

Do I need a permit to build in Peoria's floodplain?
Yes. Sec. 12-5 requires a development permit from the director of public works before any development begins in the Special Flood Hazard Area, and the director will not issue it unless the project meets Chapter 12's requirements, including site drawings and elevation data.
What counts as development requiring a floodplain permit in Peoria?
Sec. 12-2 defines development broadly: new construction or additions over $1,000, installing manufactured homes or long-term travel trailers, utility or road work, levees, walls, fences, bridges, culverts, grading, dredging, filling, and material storage all qualify.
What happens if I develop in the SFHA without a permit?
Sec. 12-11 treats it as a violation. After a ten-day notice to correct goes unanswered, the city can seek a court injunction, and a conviction carries a fine of not less than $50.00, with each day of continued violation a separate offense.

Sources & Official References

Other rules in Peoria

All Peoria rules

Compare Peoria to another location·View the Illinois environmental rules overview

Get notified when Flood Zones in Peoria, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.