Key Facts

Exempt impervious threshold
1,000 sq ft or less
Partial exemption threshold
1,001-5,000 sq ft (peak rate only)
BMP inspection frequency
Annual for 5 yrs, then every 3 yrs
Max fine per violation
$1,000.00 per day, misdemeanor
Appeal deadline
30 days to Zoning Hearing Board
Revoked permit
Cannot be reinstated, must reapply

Summary

Bensalem Township regulates stormwater under Chapter 196, requiring a site plan and permit for most land development and earth disturbance. Projects creating over 1,000 square feet of new impervious surface must control runoff volume and peak rate; violations carry misdemeanor fines up to $1,000 per day.

Sec. 196-6. - Exemptions. (a)Regulated activities that create impervious surfaces smaller than or equal to 1,000 square feet do not have to apply the volume control requirements of this chapter. Regulated activities of this size are exempt from the peak rate control requirements and the SWM site plan preparation located in article IV of this chapter. ... (b)Regulated activities that create impervious surfaces between 1,001 square feet up to and including 5,000 square feet are exempt only from the peak rate control requirements of this chapter. ... Sec. 196-130. - Penalties. (a)Any person violating the provisions of this chapter shall ... guilty of a misdemeanor and upon conviction, shall be subject to a fine of not more than $1,000.00 for each violation recoverable with costs. Each day that the violation continues shall constitute a separate offense and the applicable fines are cumulative.

Full Breakdown

Township Code § 196-5 subjects all regulated activities affecting stormwater runoff, including land development, subdivisions, new or reconstructed impervious surfaces, new buildings, redevelopment and channel diversions, to Chapter 196. Section 196-6 exempts activities creating 1,000 square feet or less of new impervious surface from volume control and site-plan requirements, and activities of 1,001 to 5,000 square feet from peak-rate control only; anything over 5,000 square feet gets no exemption, per Table 106.1. Agricultural activity and forest management are exempt from peak-rate and site-plan rules if performed under 25 Pa.

Code Chapter 102, and the Township Engineer, with Council's concurrence, may waive a mandatory provision for hardship under § 196-6(h). Section 196-127 requires landowners or their designees to inspect stormwater BMPs annually for the first five years, then every three years, and after any ten-year or greater storm. Enforcement under § 196-128 lets the Municipality order compliance by written notice specifying required remedies (monitoring, ending prohibited discharges, remediation, fines for costs, BMP implementation) and a correction deadline; failing to comply lets the Township do the work itself and bill the violator, on top of Chapter 196 penalties.

Section 196-129 allows the Township to suspend or revoke a stormwater permit for noncompliance, a chapter violation, or creating a hazard or nuisance; a revoked permit cannot be reinstated, only reapplied for. Fees for SWM site plan review and inspection are set by Board of Supervisors resolution under § 196-86, and no work permit issues until those fees are paid.

Violations & Fines

Section 196-130(a) makes any Chapter 196 violation, including unreasonable delay in allowing Township access to a stormwater facility, a misdemeanor punishable by a fine up to $1,000.00 per violation plus costs, with each day of continued violation a separate offense. The Township Solicitor may also seek injunctive relief, mandamus or other equitable remedies under § 196-130(b). Appeals from a Township or designee decision go to the Zoning Hearing Board within 30 days under § 196-131(a), citing MPC § 909.1(9).

Frequently Asked Questions

Does Bensalem require a stormwater permit for small projects?
Projects creating 1,000 square feet or less of new impervious surface are exempt from the site-plan and volume-control requirements of Chapter 196 under § 196-6(a). Between 1,001 and 5,000 square feet, only the peak-rate control requirement is exempted; over 5,000 square feet, no exemption applies.
How often must stormwater BMPs be inspected in Bensalem?
Section 196-127 requires the landowner or designee to inspect stormwater best management practices annually for the first five years, then once every three years after that, and also immediately after any storm of ten-year frequency or greater.
What is the penalty for a stormwater violation in Bensalem?
Section 196-130(a) makes a Chapter 196 violation a misdemeanor carrying a fine of up to $1,000.00 per violation plus costs, with each day the violation continues counted as a separate offense. The Township can also seek an injunction through its Solicitor.

Sources & Official References

Other rules in Bensalem

All Bensalem rules

Compare Bensalem to another location·View the Pennsylvania environmental rules overview

Get notified when Stormwater Management in Bensalem, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.