Key Facts

Design standard
Must follow City Design and Construction Manual
Detention trigger
Required if project worsens downstream drainage
Maintenance duty
Developer/HOA maintains stormwater/BMP facilities long-term
Floodplain check
Engineer must confirm compliance with flood ordinances
FEMA map cost
Owner pays for any required FIRM map revision

Summary

In the City of Blue Springs, Missouri, Section 406.050 of the UDC requires stormwater systems to be designed to the City's Design and Construction Manual, directs developers to reduce runoff velocity and preserve natural drainage as open space, and makes the developer and any homeowners' association responsible for maintaining on-site stormwater and BMP facilities indefinitely.

In the planning and design of stormwater management systems in the City of Blue Springs, the design criteria set forth in the latest edition of the Blue Springs, Missouri, Design and Construction Manual shall be used. This document is hereby referenced and made a part of this Chapter as though expressly incorporated herein. ... Where the stormwater management plan, as approved by the Director of Public Works, indicates that the proposed development will aggravate downstream drainage or flooding problems, provisions shall be included in the design of storm drainage improvements for the temporary controlled detention of stormwater runoff and its regulated discharge to the downstream storm drainage system. ... Except as otherwise expressly provided below for the public portion of the stormwater system, the developer and its successors and assigns, including the Homeowners' Association, shall at all times adequately maintain the stormwater management system and the BMP facilities as approved for the development in the approved plans.

Full Breakdown

Blue Springs handles stormwater design under Section 406.050, Drainage System, in the subdivision regulations of Chapter 406. The City incorporates its Design and Construction Manual by reference as the governing engineering standard for every stormwater management system, and it is City policy to encourage owners to lay out streets, blocks, lots, parks, and open space to slow overland flow, maximize infiltration, and preserve existing streams, channels, detention basins, and floodplain areas as open space. When the Director of Public Works determines a proposed project will aggravate downstream drainage or flooding, the developer must design temporary controlled detention facilities that regulate discharge into the downstream storm system.

Where a project touches a mapped floodplain, the engineer preparing the stormwater plan must confirm compliance with the City's other floodplain ordinances and consult the FEMA flood insurance study; any resulting change to the flood insurance rate maps is submitted to FEMA at the owner's expense. Once built, responsibility for the system does not end at acceptance: Section 406.050(D) makes the developer, its successors, and any Homeowners' Association jointly responsible for keeping the stormwater management system and BMP facilities in good working condition so they perform as designed.

Related standards in Section 406.070 require an erosion control plan approved by the Director of Public Works before construction starts and proof the project has obtained an NPDES permit from the Missouri Department of Natural Resources.

Violations & Fines

Failing to build stormwater or BMP facilities to the approved plans, skipping the required detention design, or letting facilities fall out of adequate maintenance is enforceable as a Development Code violation under Chapter 410, with the City able to withhold or revoke permits, stop work, or seek injunctive or abatement relief under Section 410.030. Absent a more specific penalty, the general penalty of Section 100.080 applies: a fine up to $500, up to 90 days imprisonment, or both, with each day of continuing noncompliance a separate offense.

Frequently Asked Questions

What stormwater design standard applies to new development in Blue Springs?
The design criteria in the City's Design and Construction Manual, incorporated by reference into UDC Section 406.050(A)(1), govern the design of all stormwater management systems.
When is stormwater detention required?
When the Director of Public Works determines a proposed development will aggravate downstream drainage or flooding, per Section 406.050(A)(3), triggering a requirement for temporary controlled detention facilities.
Who maintains stormwater facilities after a subdivision is built?
The developer and its successors, including any Homeowners' Association, under Section 406.050(D), which requires the stormwater management system and BMP facilities be kept in good working order indefinitely.
Does building near a floodplain add extra stormwater requirements?
Yes. Section 406.050(B) requires the engineer to confirm compliance with the City's floodplain ordinances and consult FEMA's flood insurance study, with the owner paying for any resulting map revision.

Sources & Official References

Other rules in Blue Springs

All Blue Springs rules

Compare Blue Springs to another location·View the Missouri environmental rules overview

Get notified when Stormwater Management in Blue Springs, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Nearby Cities