Neenah, WI Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Permit trigger
4,000 sq ft of disturbance
Sediment cap (permitted, 1+ acre)
5 tons/acre/year
Administered by
Community Development Dept
Enforced by
Public Works Department

Summary

Neenah requires an erosion-control permit for any construction site disturbing 4,000 square feet or more of land, and permitted sites over an acre must hold sediment discharge to five tons per acre a year, under Municipal Code § 22-260.

A permit is required for a construction site with 4,000 square feet or greater of land disturbing construction activity. The responsible party shall comply with all applicable provisions of this article for a permitted site, including the Subsection 22-292(b) performance standards, Section 22-293 permit requirements, and Section 22-294 plan requirements.b.A permit is not required for a construction site with less than 4,000 square feet of land disturbing construction activity.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 44).

Full Breakdown

Neenah Municipal Code § 22-260(a)(1) sets the trigger: a stormwater/erosion-control permit is required once land-disturbing construction activity reaches 4,000 square feet, while smaller sites must still follow best-management-practice performance standards without a permit. For permitted sites of an acre or more, § 22-292(b) adds a numeric ceiling, no more than five tons of sediment per acre per year, to the maximum extent practicable, from initial grading through final stabilization. One- and two-family homes disturbing under an acre and not part of a larger development are exempt from the City permit and instead fall under the state Uniform Dwelling Code. The Community Development Department administers the permit and Public Works enforces it, per Ord. No. 2017-08.

Violations & Fines

The administering authority can issue a stop-work or cease-and-desist order; after-the-fact permits are billed at double the fee, and unresolved sediment violations can be assessed against the property.

Frequently Asked Questions

Does Neenah require a permit before grading or excavation work?
Yes, once the disturbed area hits 4,000 square feet. Section 22-260(a)(1) requires an erosion-control permit above that threshold; smaller sites still must use erosion best management practices.
Is building a new house in Neenah exempt from the stormwater permit?
Often, yes: one- and two-family homes disturbing under an acre and not part of a larger development are exempt under § 22-260(a)(2)a, and instead follow the state Uniform Dwelling Code.

Sources & Official References

Other rules in Neenah

All Neenah rules

Compare Neenah to another location·View the Wisconsin environmental rules overview

Get notified when Stormwater Management in Neenah, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.