Pottstown, PA Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing law
Chapter 9, Part 2, MS4 Stormwater Management Ordinance
Permit required
Approved SWM site plan before work begins
Exemption threshold
Earth disturbance under 1,600 square feet
Maximum fine
$1,000 per violation, each day separate
Appeal deadline
30 days to Borough, then 30 days to court
Enforcing office
Borough of Pottstown (municipality)

Summary

Pottstown regulates stormwater runoff under the Borough of Pottstown MS4 Stormwater Management Ordinance, Chapter 9, Part 2. Any regulated earth-disturbance or land-development activity needs Borough approval of a stormwater management (SWM) site plan before work begins, unless the disturbance is smaller than 1,600 square feet. Violators face summary-offense fines and the approved plan must stay on site throughout construction.

This Part 2 shall be known and may be cited as the "Borough of Pottstown MS4 Stormwater Management Ordinance." ... For all regulated activities, unless preparation of an SWM site plan is specifically exempted in § 9-222: ... Preparation and implementation of an approved SWM site plan is required. ... No regulated activities shall commence until the municipality issues written approval of an SWM site plan, which demonstrates compliance with the requirements of this Part 2. ... Anyone violating the provisions of this Part 2 shall be guilty of a summary offense and, upon conviction, shall be subject to a fine of not more than $1,000 for each violation, recoverable with costs. Each day that the violation continues shall be a separate offense, and penalties shall be cumulative.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 5012545; v22 updated 2026-07-13; through 07-13-2026).

Full Breakdown

Chapter 9, Part 2 was relocated without amendment from former Chapter 26, Part 2, and now governs every 'regulated activity' affecting stormwater runoff in the Borough, including land development and earth-disturbance work covered by the Zoning Ordinance (Chapter 27) and the Subdivision and Land Development Ordinance (Chapter 22). Section 9-221 requires a Borough-approved SWM site plan before any regulated activity commences, and that approved plan has to remain on site for the whole job. Design has to meet Title 25 of the Pennsylvania Code, the Clean Streams Law and the Storm Water Management Act (Act 167), and the Borough may approve alternative measures only after consulting the Pennsylvania Department of Environmental Protection.

Section 9-222 exempts regulated activities that disturb less than 1,600 square feet from the volume- and rate-control requirements of §§ 9-223 and 9-224, and separately exempts agricultural and forest-management or timber operations that follow 25 Pa. Code Chapter 102. The Borough reviews and approves plans under §§ 9-231 through 9-237, requires completed operation-and-maintenance agreements for installed best-management practices under § 9-242, and can require a performance guarantee under § 9-243. Roof drains, sump pumps and other prohibited discharges into the storm system are addressed under §§ 9-261 and 9-262.

Section 9-273 gives the Borough enforcement authority and § 9-274 lets it suspend or revoke an approval, on top of the right-of-entry and inspection powers in §§ 9-271 and 9-272. Anyone aggrieved by a Borough decision can appeal to the Borough within 30 days under § 9-276, and then to the Montgomery County Court of Common Pleas within another 30 days.

Violations & Fines

Violating any provision of Chapter 9, Part 2 is a summary offense under § 9-275, punishable by a fine of up to $1,000 per violation plus costs of prosecution, and each day the violation continues counts as a separate offense with penalties that add up. The Borough can also seek an injunction, a writ of mandamus, or any other court order to force compliance, on top of the fine.

Frequently Asked Questions

Do I need a stormwater permit for a small home project in Pottstown?
Not if the earth disturbance is under 1,600 square feet total. Section 9-222 exempts small regulated activities from the volume- and rate-control design requirements in §§ 9-223 and 9-224, though larger or staged projects still need Borough review under § 9-221 before any work starts.
What law covers stormwater management in the Borough of Pottstown?
The Borough of Pottstown MS4 Stormwater Management Ordinance, codified at Chapter 9, Part 2 of the Borough Code. It was relocated there without amendment from the former Chapter 26, Part 2, and implements Pennsylvania's Act 167 Stormwater Management Act and the Municipalities Planning Code.
What happens if I start grading without an approved SWM site plan?
You are committing a summary offense under § 9-275, punishable by up to $1,000 per violation with each day treated separately, plus costs of prosecution. The Borough can also go to court for an injunction or mandamus order to stop the work or force compliance.
Can I appeal a Borough decision on my stormwater plan?
Yes. Section 9-276 gives you 30 days to appeal a Borough decision to the municipality itself, and if that appeal fails you get another 30 days to take it to the Montgomery County Court of Common Pleas.

Sources & Official References

Other rules in Pottstown

All Pottstown rules

Compare Pottstown to another location·View the Pennsylvania environmental rules overview

Get notified when Stormwater Management in Pottstown, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.