Royal Oak, MI Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Exemption threshold
Under 0.14 acre or 6,100 sq ft
Storm design standard
100-year, 24-hour storm event
Release rate cap
1.0 cfs/acre (2 acres or less)
Large-site release rate
0.15 cfs/acre (100+ acres)
Enforcement
City Engineer plan review and approval

Summary

New development, renovation or additions in the City of Royal Oak must detain stormwater on-site under Royal Oak City Code § 644-4, except in the Central Business District and on one- and two-family residential lots. Projects under 0.14 acre or 6,100 square feet get a temporary exemption, and systems must hold a 100-year, 24-hour storm with release rates capped by acreage.

Any development, renovation or addition to an existing development within the City, excluding property in the Central Business District Zones and properties used for one- and two-family residential purposes, shall detain the stormwater runoff from the improvement on-site. ... ... A. Developments, renovations or additions less than 0.14 acre or 6,100 square feet in area will not require stormwater detention at the time of the improvement. ... ... C. Detention Flood Control with orifice or pumped outlets shall be required to hold the volume for a 100-year, 24-hour storm event. ... The variable release rate is ... capped at 1.0 cubic foot per second (cfs) per acre for developments two acres or less. For all developments equal to or greater than 100 acres, the variable release rate is 0.15 cfs per acre.

Full Breakdown

Chapter 644, rewritten in its entirety by Ordinance No. 2026-03, requires any development, renovation or addition within Royal Oak to detain stormwater runoff on-site, with the City Engineer administering the requirement (§ 644-4). The exemption in § 644-5A covers only small projects: developments, renovations or additions under 0.14 acre or 6,100 square feet do not need detention at the time of the work, but the owner must record a lien with the City stating that once accumulated improvements exceed that threshold, the detention requirement kicks in on the combined area.

Section 644-6 sets the design target once the threshold is crossed: systems must provide Channel Protection Rate Control (extended detention) for a 1.9-inch rainfall event dewatered over 48 hours, plus Detention Flood Control sized to hold a 100-year, 24-hour storm event. The variable release rate that controls how fast water can leave the site is capped at 1.0 cubic foot per second per acre for developments of two acres or less, dropping to 0.15 cfs per acre for developments of 100 acres or more, with the City Engineer able to require an even lower rate depending on downstream capacity.

Green infrastructure such as bioretention, rain gardens, bio-swales or pervious pavement can substitute for part of the requirement under § 644-7 on sites of an acre or larger where soil infiltration rates support it. Every submittal must carry a Michigan-licensed professional engineer's seal (§ 644-8A) and go to the City Engineering Division for review before construction, with the applicant covering the City's review and inspection costs.

Violations & Fines

Chapter 644 is enforced through the City Engineer's plan-review and approval process rather than a standalone fine schedule: work that skips required stormwater detention, the recordable lien for an exempt small project, or Engineer approval before construction can be held up or denied City approval under §§ 644-4 through 644-9 until the detention system and paperwork are corrected.

Frequently Asked Questions

Does every new driveway or addition in Royal Oak need stormwater detention?
Only if the development, renovation or addition covers 0.14 acre (6,100 square feet) or more; smaller projects get a temporary exemption under § 644-5A, though the owner must record a lien so detention is required once accumulated work crosses that size.
What storm event does Royal Oak design detention systems for?
Section 644-6C requires Detention Flood Control sized for a 100-year, 24-hour storm event, plus Channel Protection Rate Control for a 1.9-inch rainfall event dewatered over 48 hours, with release rates capped at 1.0 cfs per acre for smaller sites.
Who reviews stormwater plans in Royal Oak?
The City Engineering Division, per § 644-8. Plans need a Michigan-licensed professional engineer's seal, and the City Engineer certifies conformity with the Royal Oak Site Plan Design Standards before construction can begin.

Sources & Official References

Other rules in Royal Oak

All Royal Oak rules

Compare Royal Oak to another location·View the Michigan environmental rules overview

Get notified when Stormwater Management in Royal Oak, MI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.