Albany, OR Fence Regulations: Retaining Walls (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Height trigger
Over 4 feet (1,219 mm), footing bottom to wall top
Surcharge trigger
Any retaining wall supporting a surcharge
Permit office
City of Albany Building Division
Code section
Albany Municipal Code § 18.04.040(3)
Permit lifespan
36 months; 180 days if work not started
First-offense penalty
Civil penalty up to $1,000 per violation

Summary

In the City of Albany, Oregon, a retaining wall over 4 feet high, measured from the bottom of the footing to the top of the wall, or any retaining wall supporting a surcharge, must be permitted and inspected under Title 18 and the Oregon Building Code. Albany Municipal Code § 18.04.040(3) sets the rule.

Pursuant to ORS 455.020(4) and adopted by local ordinance, the scope of the Oregon Building Code has been amended to include the following local requirements and shall be permitted and inspected pursuant to this title and the Oregon Building Code. ... (3) Retaining walls that are over 4 feet (1,219 mm) in height measured from the bottom of the footing to the top of the wall or any retaining wall supporting a surcharge.

Full Breakdown

Albany adds retaining walls to the scope of its building regulations through section 18.04.040. Under ORS 455.020(4) the city amended the scope of the Oregon Building Code to include local requirements, and the section says those items "shall be permitted and inspected pursuant to this title and the Oregon Building Code." Paragraph (3) covers retaining walls over 4 feet (1,219 mm) in height, measured from the bottom of the footing to the top of the wall, and any retaining wall supporting a surcharge. The measurement runs from the footing, not from finished grade, so buried footing depth counts toward the 4 feet. A wall of any height that carries a surcharge is caught even if it is shorter.

The permit process is the general one in Chapter 18.06. Section 18.06.020 requires the applicant to apply to the City of Albany Building Division, describe the work, give the legal description or street address, state the use, and attach plans, diagrams, calculations, and specifications as the building official requires. Under section 18.06.030 the building official can require plans, computations, and specifications to be prepared by an engineer or architect licensed by the state as state law requires, and can ask the applicant to show that state law does not require a licensed designer. Section 18.04.100 lets the building official require tests or engineering reports as proof of compliance, at no expense to the city.

Once a permit issues, section 18.08.010 keeps the work accessible and exposed until the building official approves it, and section 18.08.080 bars work beyond each inspection point without approval. Section 18.06.090 makes a permit expire 36 months after issuance, or 180 days after issuance if work has not started, or when 180 consecutive days pass without a required inspection.

Section 18.04.060(3) adds that nothing in Title 18 permits a use of land or structure that is not in accordance with the Albany Development Code, so a wall still has to satisfy the city's separate zoning rules.

Violations & Fines

Building a wall that needs a permit without one triggers an investigation under section 18.06.100, with an investigation fee in addition to the permit fee, and the building official can issue a stop work order under section 18.10.060. Section 18.10.210 sets civil penalties for a first offense of up to $1,000 per violation, $2,500 for a second offense within 3 years, and $5,000 for later offenses, plus up to $1,000 per day for continued violations.

Frequently Asked Questions

How is retaining wall height measured in Albany, Oregon?
Section 18.04.040(3) measures height from the bottom of the footing to the top of the wall, and a wall over 4 feet (1,219 mm) on that measure needs a permit and inspection. The measurement starts at the footing, so it is not the same as the height visible above the ground on the low side.
Does a short retaining wall ever need a permit in the City of Albany, Oregon?
Yes. The same paragraph covers any retaining wall supporting a surcharge, whatever its height. A wall holding up a driveway, a structure, or other added load falls under Title 18 and the Oregon Building Code even when it is under 4 feet.
Will Albany require an engineer for a retaining wall?
Section 18.06.030 allows the building official to require plans, computations, and specifications prepared by an engineer or architect licensed by the state, as state law requires. Section 18.04.100 also allows the official to require tests or engineering reports as proof of compliance when evidence is insufficient.
What if a wall was built without a permit in Albany?
Section 18.06.100 requires an investigation before a permit issues, with an investigation fee on top of the permit fee unless waived. The fee is appealable under Chapter 18.14 AMC, and paying it does not excuse any other violation or penalty under Title 18.

Sources & Official References

Other rules in Albany

All Albany rules

Compare Albany to another location·View the Oregon fence regulations overview

Get notified when Retaining Walls in Albany, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.