Dallas, TX Historic Preservation: HCM Demolition Controls (2026)
Key Facts
- Minimum building age
- 50 years old
- Phase I review deadline
- 10 days to assess criteria
- Phase II meeting deadline
- Within 45 days of determination
- Public notice sign deadline
- 2 working days after determination
- Outcome after 45 days if no deal
- Permit must be granted
Summary
For historically significant buildings outside a historic overlay district, Dallas can impose a demolition delay overlay under Sec. 51A-4.504 that pauses a demolition permit for at least 45 days so the owner and city officials can discuss preservation alternatives before the building official may issue the permit.
(a) Purpose. A demolition delay overlay district is intended to encourage the preservation of historically significant buildings that are not located in a historic overlay district by helping the property owner identify alternatives to demolition. (b)(2) This section applies to any building located in a demolition delay overlay district that is at least 50 years old and meets one of the following criteria: (A) the building is located in a National Register Historic District or is individually listed on the National Register of Historic Places; (B) the building is designated as a Recorded Texas Historic Landmark; (C) the building is designated as a State Antiquities Landmark; (D) the building is designated as a National Historic Landmark.
Full Breakdown
Sec. 504 creates a demolition delay overlay district for buildings at least 50 years old that are not inside a historic overlay district but meet one of five criteria: listed on or located in a National Register Historic District, designated a Recorded Texas Historic Landmark, a State Antiquities Landmark, a National Historic Landmark, or identified as individually significant or contributing in a historic resources survey conducted under National Register or Texas Historical Commission guidelines. The city plan commission or city council can create such a district through the standard zoning amendment procedure.
Once a demolition application is filed for a qualifying building, Phase I requires the building official to refer it to the historic preservation officer, who has 10 days to determine whether the building meets the delay criteria; if it doesn't, and the application otherwise satisfies the Dallas Building Code, the permit is granted. If it does meet the criteria, Phase II starts: within 45 days the historic preservation officer must convene a meeting between the owner and city officials to discuss alternatives such as historic designation, tax exemptions and economic development incentives, loans or grants, acquisition of the building, or variances, and within two working days of the qualifying determination a sign must go up on the property with a public phone number.
If the 45-day period ends with the building code requirements met and the owner declining any agreement, the building official must grant the demolition permit. Phase III lets the owner voluntarily agree with the city to extend the delay further while alternatives are explored.
Violations & Fines
The ordinance is procedural rather than punitive: it does not authorize the city to deny a compliant demolition permit outright, only to delay issuance while alternatives are discussed. Proceeding with demolition without going through the referral and delay steps, or without the required permit, is enforced as a building-code and zoning violation under the city's general penalty, Sec. 13-1(a)(2), fined up to $2,000 per day.
Frequently Asked Questions
Does a demolition delay overlay stop me from tearing down an old building in Dallas?
Which buildings does the Dallas demolition delay overlay apply to?
What happens during the demolition delay meeting?
Sources & Official References
Other rules in Dallas
Texas rules heatmap·Compare Dallas to another location·View the Texas historic preservation overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.