Key Facts
- Governing section
- Smyrna Code Sec. 54-64
- AO zone depths
- Base flood depths of one to three feet above ground
- Elevation with mapped depth
- To the FIRM flood depth number above highest adjacent grade
- Elevation with no mapped depth
- At least three feet above highest adjacent grade
- Nonresidential flood-proofing
- Water tight to FIRM flood level plus one foot
- Certifier of floor elevation
- The city engineer, kept in the permit file
Summary
In the City of Smyrna, Georgia, buildings in AO shallow flooding zones must have the lowest floor raised to the flood depth number printed on the flood insurance rate map, measured above the highest adjacent grade, or at least three feet above it when the map lists no depth. Sec. 54-64 also requires drainage paths that steer floodwater away from the structure.
Areas of special flood hazard established in section 54-7, may include designated "AO" shallow flooding areas. These areas have base flood depths of one to three feet above ground, with no clearly defined channel. The following provisions apply: (1)All new construction and substantial improvements of residential and non-residential structures shall have the lowest floor, including basement, elevated to the flood depth number specified on the flood insurance rate map (FIRM), above the highest adjacent grade. If no flood depth number is specified, the lowest floor, including basement, shall be elevated at least three feet above the highest adjacent grade. Openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of section 54-61(4). ... (3)Drainage paths shall be provided to guide floodwater around and away from any proposed structure.
Full Breakdown
Sec. 54-64 of the Smyrna Code covers areas of shallow flooding, which are designated AO zones inside the areas of special flood hazard. The Code describes these areas as having base flood depths of one to three feet above ground with no clearly defined channel. For all new construction and substantial improvements, residential and non-residential, the lowest floor, including basement, must be elevated to the flood depth number specified on the flood insurance rate map (FIRM), above the highest adjacent grade. If no flood depth number is specified, the lowest floor must be elevated at least three feet above the highest adjacent grade. Openings that let floodwater move unimpeded must follow the standards of Sec. 54-61(4), and the city engineer certifies the lowest floor elevation, which becomes a permanent part of the permit file.
Nonresidential buildings can be flood-proofed in lieu of elevation. The structure and its attendant utility and sanitary facilities must be designed water tight to the specified FIRM flood level plus one foot, above the highest adjacent grade, and a registered professional engineer or architect must certify the design. Sec. 54-64(3) adds that drainage paths shall be provided to guide floodwater around and away from any proposed structure.
Streams with no published base flood data are handled in Sec. 54-63. The city engineer first obtains and uses any scientific or historic base flood elevation and floodway data available from a federal, state or other source. Only if none exists does the fallback apply: the lowest floor of the lowest enclosed area, basement included, must be elevated no less than three feet above the highest adjacent grade at the building site.
For subdivisions, Sec. 54-65(d) requires base flood elevation data for proposals and other development, including manufactured home parks and subdivisions, greater than 50 lots or five acres, whichever is less.
Violations & Fines
Elevation violations fall under Sec. 54-13: a misdemeanor, with a fine of not more than $2,500.00 on conviction plus costs and expenses, and each day the violation continues counted as a separate offense. The city engineer can also issue a stop-work order when the lowest-floor certification is not submitted or its deficiencies are not corrected. Variances require notice of the elevation difference and the resulting insurance cost.
Frequently Asked Questions
What is an AO zone under Smyrna's flood ordinance?
How high must the floor be in an AO zone?
What if a stream has no base flood elevation data?
Can a nonresidential building flood-proof in an AO zone?
Sources & Official References
Other rules in Smyrna
Compare Smyrna to another location·View the Georgia hurricane preparedness overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.