Tree removal permit rules in Highlands County, FL, sometimes called heritage tree, protected tree, or street tree ordinances, list which trees require a permit before you can cut them down.

Key Facts

Permit required
Land clearing permit before any building permit
Triggers full ECR review
Listed species/resource found on site
Agricultural exemption
Bona fide ag operations on ag-designated land
Exemption tradeoff
3-year bar on non-ag development after clearing
Illegal clearing penalty
Mitigation fee plus 3-year clearing/development bar

Summary

Clearing trees and vegetation on development sites in unincorporated Highlands County requires a county land clearing permit whenever natural, archaeological or historical resources are known to exist on the property. Highlands County Code § 12.12.620 ties that permit to the county's environmental clearance process and imposes real penalties, including a three-year building freeze, for clearing land illegally.

These county ordinances apply to unincorporated areas of Highlands County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

C.Land clearing permits. ... Land clearing permits are required for approval of all building permits. Except as provided in section 12.12.620.E. of this division and the land clearing definition in sections 12.12.620.A. and B. above, no land clearing shall be allowed to commence on a site where natural, archaeological, or historical resources are known to exist without first obtaining a county land clearing permit. ... F.Penalties for illegal land clearing. The county, in consultation with the property owner, shall impose one or more of the following penalties as appropriate if land is cleared without appropriate environmental clearance review or a county land clearing permit:1.A penalty mitigation fee shall be imposed based on a set of fees approved by the BCC, based on the amount of land cleared; or2.No development or additional land clearing shall be permitted for a period of three years after such clearing; or3.The vegetation shall be replaced or the habitat allowed to restore itself through development and implementation of a management plan.

Full Breakdown

620(B) exempts certain listed activities from needing a permit even on parcels shown on the county's conservation overlay map. 611, such as scrub jays, gopher tortoises or listed scrub plants endemic to the Lake Wales Ridge, the permit is issued only in accordance with the county's environmental clearance regulations. 604. 620(E) carves out a genuine agricultural exemption for bona fide agricultural operations clearing land they own for crops, silviculture or livestock on property designated agricultural, but that exemption comes with a three-year lock-out on any non-agricultural development order for the same site after the clearing is finished. 620(D) for obtaining any state or federal permits needed before clearing land where a protected resource exists.

Violations & Fines

Section 12.12.620(F) lets the county impose a penalty mitigation fee based on a BCC-approved fee schedule tied to the amount of land cleared, bar all development or additional clearing on the site for three years, require replacement of the vegetation or restoration of the habitat through a management plan, and penalize a land clearing company or contractor who clears without a permit on an owner's behalf; penalty fees collected are deposited into the county's conservation trust fund, and the decision to impose a penalty can be appealed under section 12.12.619(J).

Frequently Asked Questions

Do I need a permit before clearing trees on my property in unincorporated Highlands County?
Generally yes if a natural, archaeological or historical resource is known to exist on the site; section 12.12.620(C) requires a county land clearing permit before any land clearing commences and before a building permit can be issued, unless your activity is exempt under the land clearing definition.
What happens if I clear land without the required permit?
Section 12.12.620(F) authorizes the county to impose a penalty mitigation fee based on how much land was cleared, bar further development or clearing on the property for three years, and require replacement or restoration of the cleared vegetation and habitat.
Is there an exemption for farmers who need to clear land?
Yes, section 12.12.620(E) exempts bona fide agricultural operations clearing land they own or lawfully occupy for crops, silviculture or livestock on property designated agricultural, but no non-agricultural development order can be approved on that same land for three years after the clearing is completed.

Sources & Official References

Other rules in Highlands County

All Highlands County rules

Florida rules heatmap·Compare Highlands County to another location·View the Florida landscaping rules overview

Get notified when Tree Removal & Heritage Trees in Highlands County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.