Skip to main content
CityRuleLookup

Peoria, AZ Noise Ordinances: Construction Hours (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Construction hours in Peoria, AZ, sometimes called construction noise rules or contractor work-hour ordinances, set when contractors can run power tools, hammers, and heavy equipment.

Key Facts

Residential zones, summer
6:00 a.m. to 7:00 p.m.
Residential zones, winter
7:00 a.m. to 7:00 p.m.
Commercial/industrial, 500+ ft from homes
5:00 a.m. to 7:00 p.m. year-round
Permit authority
Building Safety Manager
Penalty
civil sanction or class one misdemeanor

Summary

Peoria limits construction noise to set daily windows that shift by season and zoning: work near homes runs 6 a.m. to 7 p.m. in summer and 7 a.m. to 7 p.m. in winter, while commercial and industrial work more than 500 feet from housing can start as early as 5 a.m. year-round. City Code Section 13-91 lets the Building Safety Manager permit different hours.

Sec. 13-91. Noise; construction. (a) Construction of buildings and other projects. (1) Noise limitations: It shall be unlawful for any person to operate equipment or perform any outside construction or repair work on buildings, structures or projects... except within the time periods specified below unless an appropriate permit has been obtained beforehand from the City. (2) Construction start/stop times: Concrete work: from April 2nd to September 29th, inclusive, concrete may be poured each day between the hours of 5:00 a.m. and 7:00 p.m. or at such other times as authorized by permit. From September 30th to April 1st, inclusive, concrete may be poured each day between the hours of 6:00 a.m. to 7:00 p.m.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-9: Supplement contains: LLocal legislation current through Ord. 2026-15, passed 6-16-26).

Full Breakdown

, unless a permit authorizes other times. from September 30 through April 1. , with no seasonal shift. Subsection (a)(3) lets the Building Safety Manager or a designee issue a permit for different hours or higher noise levels, weighing factors such as neighborhood population and sleep patterns, traffic impacts, the noise level of the specific work, and public interest; no permit is required for emergency work needed to prevent or address physical trauma or property damage. The permit must be kept on site and shown to city officials on request, and subsection (a)(4) lets the Building Safety Manager revoke a permit on substantial evidence that the work is causing significant disturbance.

Violations & Fines

Operating construction equipment or performing outside construction or repair work beyond the permitted hours in Section 13-91, without an approved permit, is enforced by the Peoria Police Department under Chapter 13's noise provisions; Section 13-103 makes an owner, responsible party or other person in control of the site who causes or permits the violation subject to a civil sanction, or in the alternative a class one misdemeanor, with each day of the violation treated as a separate offense.

Frequently Asked Questions

What time can construction start near my house in Peoria?
Construction near homes follows a seasonal clock. City Code Section 13-91(a)(2) bars work in, or within 500 feet of, a residential zone before 6:00 a.m. from April 2 through September 29, and before 7:00 a.m. from September 30 through April 1, unless the crew holds a permit for different hours.
Can construction happen earlier away from houses?
Yes. Section 13-91(a)(2) allows construction and repair work in commercial and industrial zones that sit more than 500 feet from any residential zone to begin as early as 5:00 a.m. year-round, with no seasonal change, though work must still stop by 7:00 p.m.
Can a contractor get permission to work outside normal hours?
Yes. Section 13-91(a)(3) lets the Building Safety Manager or a designee issue a permit for different construction hours or higher noise levels, weighing factors like neighborhood sleep patterns and traffic impact, and the Manager can revoke that permit under subsection (a)(4) if the work causes a significant disturbance.

Sources & Official References

Other rules in Peoria

All Peoria rules

How Peoria compares: Cities with the Strictest Construction Hours·Compare Peoria to another location·View the Arizona noise ordinances overview

Get notified when Construction Hours in Peoria, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Construction Hours in Nearby Cities

How other cities in Maricopa County handle construction hours.

Chandler, AZ
Some Restrictions
Glendale, AZ
Some Restrictions
Surprise, AZ
Some Restrictions
Goodyear, AZ
Some Restrictions
Scottsdale, AZ
Some Restrictions
Tempe, AZ
Some Restrictions
Phoenix, AZ
Some Restrictions
Mesa, AZ
Some Restrictions