Bartow County, GA Outdoor Lighting: Dark Sky Rules (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Fixture type required
Full cut-off only
Max pole height
25 feet
Pole setback from property line
10 feet minimum
Max illumination at property line
0.5 foot-candles
Scope
Data centers only, not county-wide
Review step
Photometric plan may be required

Summary

Bartow County has no general outdoor lighting ordinance for unincorporated homes and businesses, but its Zoning Ordinance imposes a specific dark-sky standard on data centers. Exterior fixtures at a data center site must be shielded, downcast and full cut-off, with poles capped at 25 feet and light spilling no more than 0.5 foot-candles past the property line.

These county ordinances apply to unincorporated areas of Bartow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

12.Exterior illumination shall be shielded, downcast, and of a luminosity designed to maintain the existing night sky darkness and to prevent light trespass onto adjacent properties. In order to obtain that objective, the following criteria shall be met:a.All fixtures shall be full cut-off type fixtures;b.Light poles shall be no taller than 25 feet in height;c.All light poles must be setback a minimum of 10 feet from any exterior property line; andd.Maximum foot-candles at the property line shall be 0.5. The zoning administrator may require a photometric lighting plan which shows conformity with these requirements as part of any building permit application.

Full Breakdown

2, paragraph 12 of the county's "data center" development standards, requires that all exterior illumination at a data center be shielded, downcast, and of a luminosity designed to maintain the existing night sky darkness and to prevent light trespass onto adjacent properties. To meet that objective, every fixture on a data center site must be a full cut-off type, meaning no light escapes above the horizontal plane of the fixture. Light poles cannot exceed 25 feet in height, and every pole must sit back at least 10 feet from any exterior property line.

5 foot-candles. Community Development, through the Zoning Administrator, may require an applicant to submit a photometric lighting plan demonstrating conformity with all four criteria before a building permit is issued, so the standard is checked at the plan-review stage rather than only after a complaint. This is a use-specific standard tied to the data center definition in Article III of the Zoning Ordinance, not a county-wide dark-sky or lighting code; residential subdivisions, general commercial centers and other uses are not held to the same shielding, pole-height or foot-candle limits unless a separate district standard or development condition imposes them. 2(12).

Violations & Fines

Failure to meet the lighting standard is enforced the same as any other Zoning Ordinance violation: the Zoning Administrator or code enforcement can cite the operator in magistrate court, or the county can seek civil fines and injunctive relief in superior court under § 13.2. Because the standard sits outside Article VI, the mandatory fine is $300 for a first violation, $500 for a second, and $1,000 for a third or later violation, with each day of noncompliant lighting counted separately.

Frequently Asked Questions

Does Bartow County have a dark-sky ordinance for all outdoor lighting?
No. The county's shielded, downcast, full cut-off lighting standard with a 25-foot pole cap and 0.5 foot-candle property-line limit applies specifically to data centers under Zoning Ordinance § 3.2(12); it is not a general county-wide lighting code for homes, farms or other commercial uses.
What fixtures satisfy the data center lighting standard?
Every exterior fixture must be a full cut-off type that is shielded and downcast so it does not add glow to the night sky or spill light onto neighboring parcels, with poles no taller than 25 feet and set back at least 10 feet from the property line.
Who checks a data center's lighting plan before construction?
Bartow County Community Development, acting through the Zoning Administrator, can require a photometric lighting plan showing the site meets the shielding, pole-height, setback and 0.5 foot-candle limits in § 3.2(12) before it issues a building permit.

Sources & Official References

Other rules in Bartow County

All Bartow County rules

Compare Bartow County to another location·View the Georgia outdoor lighting overview

Get notified when Dark Sky Rules in Bartow County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.